What is the perfect number of hours a Developer should work in a week?
What is the perfect number of hours a Developer should work in a week?A . As long as it is needed. B. A maximum of 40 hours per week. C. It is required to work at a constant pace. D. Between 40 and 60 hours per week.View AnswerAnswer: C Explanation:...
Which of the following answers can be reasons for the Scrum Master to attend the Daily Scrum?
Which of the following answers can be reasons for the Scrum Master to attend the Daily Scrum?A . To be able to track the Sprint progress. B. It is not necessary for the Scrum Master to attend the meeting. C. To support the Product Owner. D. The developers have asked...
What is the main role of a QA in Scrum?
What is the main role of a QA in Scrum?A . Support to have less technical debt. B. Support the testers in the process. C. There are no QA's in Scrum.View AnswerAnswer: C Explanation: There are only the Roles: Product Owner, Scrum Master and Developer.
The Sprint Backlog content is emerging during the Sprint.
The Sprint Backlog content is emerging during the Sprint.A . True B. FalseView AnswerAnswer: A Explanation: There are 3 things in a Sprint Backlog:
How many developers are in a scrum team?
How many developers are in a scrum team?A . 3 to 10 B. 1 to 9 C. 3 to 9View AnswerAnswer: C Explanation: The recommended size of the team is 3 to 9 according to the Scrum Guide and Scrum.org.
When n Scrum teams are working on a product, there should always be only 1 Product Owner but 1-n Scrum Masters.
When n Scrum teams are working on a product, there should always be only 1 Product Owner but 1-n Scrum Masters.A . False B. TrueView AnswerAnswer: B Explanation: When there are n teams in a project, there are: - 1 Product Backlog - n Sprint Backlogs each Sprint - 1...
What is the main accountability (roles = outdated term) of a Project Manager in Scrum?
What is the main accountability (roles = outdated term) of a Project Manager in Scrum?A . Supporting the Product Owner. B. Tracking the progress of a Release. C. There are no Project Managers in Scrum. D. Managing Risks.View AnswerAnswer: C Explanation: There are no Project Managers in Scrum.
The Sprint Review is considered as a "formal meeting".
The Sprint Review is considered as a "formal meeting".A . True B. FalseView AnswerAnswer: B Explanation: Be careful with the word "formal". Scrum. org uses the word "formal" in two different ways:
What does a burn-down chart measure in a project?
What does a burn-down chart measure in a project?A . Work remaining across time. B. Business value delivered by the team. C. Budget remaining across time.View AnswerAnswer: A
What may happen if the Scrum Teams composition changes during the project?
What may happen if the Scrum Teams composition changes during the project?A . The productivity will increase due to new ideas. B. The roles are clearly defined - nothing will happen. C. Often a short-term reduction in productivity can be seen.View AnswerAnswer: C Explanation: It is okay to change the...