The Sprint Review is considered as a "formal meeting".
The Sprint Review is considered as a "formal meeting".A . True B. FalseView AnswerAnswer: B Explanation: Be careful with the word "formal". Scrum. org uses the word "formal" in two different ways:
Please select the answer representing a responsibility of a Product Owner.
Please select the answer representing a responsibility of a Product Owner.A . Ordering the items in the Product Backlog to best achieve goals and missions. B. Defining the Definition of Done. C. Defining the Definition of Ready.View AnswerAnswer: A Explanation: There is no Definition of Ready in Scrum.
Which of the following should not be changed during a Sprint?
Which of the following should not be changed during a Sprint?A . Product Backlog. B. Definition of Done. C. The Sprint Backlog.View AnswerAnswer: B Explanation: The Sprint Backlog is always changing as the Sprint Backlog items are decomposed into tasks. The Product Backlog is refined during the Sprint and also...
Which of the following is a Scrum Value?
Which of the following is a Scrum Value?A . Creativity B. Inspection C. Adaption D. FocusView AnswerAnswer: D Explanation: The Scrum Values are: commitment, courage, focus, openness, and respect.
Which statement is not correct about the Scrum Daily?
Which statement is not correct about the Scrum Daily?A . It is moderated by the Product Owner. B. The developers have to participate in the meeting. C. It is a time boxed event (15 min). D. It should be held at the same time and place.View AnswerAnswer: A Explanation: It...
Which questions does the Sprint Planning answer?
Which questions does the Sprint Planning answer?A . What can be delivered in the Increment resulting from the upcoming Sprint? B. Who will do which Sprint Backlog item? C . How will the work needed to deliver the Increment be achieved?View AnswerAnswer: A,C Explanation: The Development Team is self-organized. That...
More Velocity means more Value!
More Velocity means more Value!A . True B. FalseView AnswerAnswer: B Explanation: There is no direct relationship between Velocity (speed) and value.
Which two of the following are not correct about non-functional requirements?
Which two of the following are not correct about non-functional requirements?A . The Project Manager takes care of non-functional requirements. B. Non-functional requirements can be added to the Product Backlog. C. Non-functional requirements are reflected in the Sprint Goal. D. Non-functional requirements can be added to the Definition of Done.View...
What should the Product Owner do when the Developers are ready to start the first Sprint, but the Product Backlog is not ready yet?
What should the Product Owner do when the Developers are ready to start the first Sprint, but the Product Backlog is not ready yet?A . The Product Owner should ask the Scrum Master to remove this impediment. B. The Product Owner should let the team start the Sprint and continue...
The Definition of Done shouldn't be changed in the middle of the Sprint.
The Definition of Done shouldn't be changed in the middle of the Sprint.A . False B. TrueView AnswerAnswer: B