What should you do?
User documentation is part of your definition of “Done”. However, there aren't enough technical writers for all teams. Your Development Team doesn't have a technical writer. What should you do?A . Form a separate team of technical writers that will work on an on-demand basis for the various Product Owners....
What are two good ways for a Scrum Team to ensure security concerns are satisfied? (Choose two.)
What are two good ways for a Scrum Team to ensure security concerns are satisfied? (Choose two.)A . Postpone the work until a specialist can perform a security audit and create a list of security-related Product Backlog items.B . Add security concerns to the definition of “Done”.C . Add a...
When many Scrum Teams are working on the same product, should all of their increments be integrated every Sprint?
When many Scrum Teams are working on the same product, should all of their increments be integrated every Sprint?A . Yes, but only for Scrum Teams whose work has dependencies.B . Yes, otherwise the Product Owners (and stakeholders) may not be able to accurately inspect what is done.C . No,...
What action should the Scrum Master take?
A Scrum Master is working with a Development Team that has members in different physical locations. The Development Team meets in a variety of meeting rooms and has much to do logistically (for example, set up conference calls) before the Daily Scrum. What action should the Scrum Master take?A ....
What is the accountability of the Product Owner during Sprint 0? (Choose the best answer.)
What is the accountability of the Product Owner during Sprint 0? (Choose the best answer.)A . There is no such thing as Sprint 0.B . Gathering, eliciting, and analyzing the requirements that will be inserted into the Product Backlog.C . Make the complete project plan to commit date, budget, and...
What happens if the Development Team cannot complete its work by the end of the Sprint?
What happens if the Development Team cannot complete its work by the end of the Sprint?A . The Sprint is extended and future Sprints use this new duration.B . The Sprint length holds and the Development Team continuously learns what is actually possible to do within a Sprint of this...
For which is the Scrum Master responsible?
For which is the Scrum Master responsible?A . Managing the performance of the Scrum Team.B . The meetings and the objectives that a Scrum Team sets for itself.C . The Scrum framework being adopted and used properly.D . Keeping track of resource allocation.View AnswerAnswer: C
Which two activities will a Product Owner engage in during a Sprint? (Choose two.)
Which two activities will a Product Owner engage in during a Sprint? (Choose two.)A . Run the Daily Scrum.B . Prioritize the Development Team’s work on the Sprint Backlog.C . Update management on what is being worked on.D . Answer QUESTION NO:s from the Development Team about items in the...
The length of a Sprint should be:
The length of a Sprint should be:A . Short enough to keep the business risk acceptable to the Product Owner.B . Short enough to be able to synchronize the development work with other business events.C . No more than one calendar month.D . All of these answers are correct.View AnswerAnswer:...
Every Scrum Team must have a Product Owner and Scrum Master. (Choose the best answer.)
Every Scrum Team must have a Product Owner and Scrum Master. (Choose the best answer.)A . True. Outcomes affected by their participation and availability.B . False. A Product Owner can be replaced by a subject matter expert in the Scrum Team.C . False. A Scrum Master is only required when...