Scrum has a role called “Project Manager”.

Scrum has a role called “Project Manager”.A . TrueB . FalseView AnswerAnswer: B

November 28, 2019 No Comments READ MORE +

How should Product Backlog items be chosen when multiple Scrum Teams work from the same Product Backlog?

How should Product Backlog items be chosen when multiple Scrum Teams work from the same Product Backlog?A . The Scrum Team with the highest velocity pulls Product Backlog items first.B . The Development Teams pull in work in agreement with the Product Owner.C . The Product Owner should provide each...

November 28, 2019 No Comments READ MORE +

Which three phrases best describe the purpose of a definition of “Done”?

A Development Team selects a set of Product Backlog items for a Sprint Backlog with the intent to get the selected items “Done” by the end of the Sprint. Which three phrases best describe the purpose of a definition of “Done”? (Choose three.)A . It controls whether the developers have...

November 27, 2019 1 Comment READ MORE +

Scrum is a methodology that tells in detail how to build software incrementally.

Scrum is a methodology that tells in detail how to build software incrementally.A . TrueB . FalseView AnswerAnswer: B

November 26, 2019 No Comments READ MORE +

Which output from Sprint Planning provides the Development Team with a target and overarching direction for the Sprint?

Which output from Sprint Planning provides the Development Team with a target and overarching direction for the Sprint?A . The Sprint Backlog.B . The Sprint GoalC . The release plan.D . Sprint Review minutes.View AnswerAnswer: B

November 25, 2019 1 Comment READ MORE +

Which answer best describes the topics covered in Sprint Planning?

Which answer best describes the topics covered in Sprint Planning?A . What to do and who will do it.B . How conditions have changed and how the Product Backlog should evolve.C . What can be done and how to do it.D . What went wrong in the last Sprint and...

November 25, 2019 No Comments READ MORE +

Which two things should the Development Team do during the first Sprint? (Choose two.)

Which two things should the Development Team do during the first Sprint? (Choose two.)A . Make up a plan for the rest of the project.B . Analyze, describe, and document the requirements for the subsequent Sprints.C . Develop at least one piece of functionality.D . Analyze, design, and describe the...

November 24, 2019 No Comments READ MORE +

Who should make sure everyone on the Development Team does his or her tasks for the Sprint?

Who should make sure everyone on the Development Team does his or her tasks for the Sprint?A . The Project Manager.B . The Product Owner.C . The Scrum Master.D . The Development Team.E . All of the above.View AnswerAnswer: D

November 24, 2019 No Comments READ MORE +

During a Sprint, when is new work or further decomposition of work added to the Sprint Backlog?

During a Sprint, when is new work or further decomposition of work added to the Sprint Backlog?A . When the Product Owner identifies new work.B . As soon as possible after they are identified.C . When the Scrum Master has time to enter them.D . During the Daily Scrum after...

November 23, 2019 No Comments READ MORE +

The purpose of a Sprint is to produce a done Increment of product.

The purpose of a Sprint is to produce a done Increment of product.A . TrueB . FalseView AnswerAnswer: A

November 22, 2019 No Comments READ MORE +