Who is responsible for managing the progress of work during a Sprint?

Who is responsible for managing the progress of work during a Sprint?A . The Scrum Master.B . The Development Team.C . The Product Owner.D . The most junior member of the Team.View AnswerAnswer: B

May 7, 2020 No Comments READ MORE +

What it the main reason for the Scrum Master to be at the Daily Scrum?

What it the main reason for the Scrum Master to be at the Daily Scrum?A . To gather status and progress information to report to management.B . To write down any changes to the Sprint Backlog, including adding new items, and tracking progress on the burn-down.C . He or she...

May 7, 2020 No Comments READ MORE +

Scrum is a methodology that tells in detail how to build software incrementally.

Scrum is a methodology that tells in detail how to build software incrementally.A . TrueB . FalseView AnswerAnswer: B

May 6, 2020 No Comments READ MORE +

Which three of the following activities would probably help the team in starting up?

You are the Scrum Master on a newly formed Scrum Team. Which three of the following activities would probably help the team in starting up? (Choose three.)A . Introduce a bonus system for the top performers in the team.B . Have the Scrum Team members introduce themselves to each other...

May 6, 2020 No Comments READ MORE +

Who must attend the Daily Scrum?

Who must attend the Daily Scrum?A . The Scrum Master and Product Owner.B . The Development Team.C . The Development Team and Product Owner.D . The Scrum Team.E . The Development Team and Scrum Master.View AnswerAnswer: B

May 6, 2020 No Comments READ MORE +

When can a Development Team cancel a Sprint?

When can a Development Team cancel a Sprint?A . It can’t. Only Product Owners can cancel Sprints.B . When functional expectations are not well understood.C . When the Product Owner is absent too often.D . When the selected Product Backlog items for the Sprint become unachievable.E . When a technical...

May 6, 2020 No Comments READ MORE +

What should the Scrum Master do?

Five new Scrum Teams have been created to build one product. A few of the developers on one of the Development Teams ask the Scrum Master how to coordinate their work with the order teams. What should the Scrum Master do?A . Teach the Product Owner to work with the...

May 6, 2020 3 Comments READ MORE +

What would be good advice to give the Product Owner?

A Development Team asks their Product Owner to re-order the Product Backlog. The team is waiting for an external supplier to deliver a specific software component. Without that component there won’t be enough work in the next Sprint to occupy the full team. The Product Owner asks the Scrum Master...

May 6, 2020 No Comments READ MORE +

When do Development Team members take ownership of a Sprint Backlog item?

When do Development Team members take ownership of a Sprint Backlog item?A . At the Sprint planning meeting.B . During the Daily Scrum.C . Never. All Sprint Backlog Items are “owned” by the entire Development Team, even though each one may be done by an individual Development Team member.D ....

May 5, 2020 No Comments READ MORE +

Which outcome is expected as Scrum Teams mature?

Which outcome is expected as Scrum Teams mature?A . They will improve their definition of “Done” to include more stringent criteria.B . The Sprint Retrospectives will grow to be longer than 4 hours.C . There is no need for a time-boxed Sprint, since time-boxes are only for new Scrum Teams.D...

May 5, 2020 2 Comments READ MORE +