A properly functioning Scrum Team will have at least one Release Sprint and may well have several.
A properly functioning Scrum Team will have at least one Release Sprint and may well have several.A . TrueB . FalseView AnswerAnswer: A
What would be three key concerns if the frequency were to be lowered to every two or three days?
The Daily Scrum is an event that happens every day. What would be three key concerns if the frequency were to be lowered to every two or three days? (Choose three.)A . Opportunities to insect and adapt the Sprint Backlog are lost.B . Impediments are raised and resolved more slowly.C...
How much time is required after a Sprint to prepare for the next Sprint?
How much time is required after a Sprint to prepare for the next Sprint?A . The break between Sprints is time-boxed to 1 week for 30 day Sprints, and usually less for shorter sprints.B . Enough time for the requirements for the next Sprint to be determined and documented.C ....
Who creates a Product Backlog Item’s estimate?
Who creates a Product Backlog Item’s estimate?A . The Development Team after clarifying requirements with the Product Owner.B . The Product Owner with input from the Development Team.C . The most senior people in the organization, including architects and subject matter experts.D . The Scrum Master.E . The Development Team,...
Which of the following two actions should the Scrum Master support?
In the Sprint Planning meeting, the Product Owner and the Development Team were unable to reach a clear understanding about the highest order Product Backlog items. Because of this, the Development Team couldn’t figure out how many Product Backlog items it could forecast for the upcoming Sprint. They were able...
How much of the Sprint Backlog must be defined during the Sprint Planning event?
How much of the Sprint Backlog must be defined during the Sprint Planning event?A . Just enough tasks for the Scrum Master to be confident in the Development Team’s understanding of the Sprint.B . The entire Sprint Backlog must be identified and estimated by the end of the Sprint Planning...
Which answer best describes the topics covered in Sprint Planning?
Which answer best describes the topics covered in Sprint Planning?A . What to do and who will do it.B . How conditions have changed and how the Product Backlog should evolve.C . What can be done and how to do it.D . What went wrong in the last Sprint and...
A Development Team is required to deliver a done Increment by the end of a Sprint. Select two statements that explain what “Done” means. (Choose two.)
A Development Team is required to deliver a done Increment by the end of a Sprint. Select two statements that explain what “Done” means. (Choose two.)A . All work the Development Team is willing to do.B . Ready for integration.C . No work left from the definition of “Done”.D ....
Which statement best describes Scrum?
Which statement best describes Scrum?A . A defined and predictive process that confirms to the principles of Scientific Management.B . A complete methodology that defines how to develop software.C . A cookbook that defines best practices for software development.D . A framework within which complex products in complex environments are...
Which two are valid actions?
As the Sprint Planning meeting progresses, the Development Team sees that the workload is greater than they can handle. Which two are valid actions? (Choose two.)A . Recruit additional Development Team members before the work can begin.B . The Development Team ensures that the Product Owner is aware, starts the...