What would be three key concerns if the frequency were to be lowered to every two or three days?

The Daily Scrum is an event that happens every day. What would be three key concerns if the frequency were to be lowered to every two or three days? (Choose three.) A The Scrum Master loses the ability to update the Gantt Chart properly. B The Sprint Plan may become...

January 18, 2021 No Comments READ MORE +

Which of the following are true about the length of the Sprint? (Choose two.)

Which of the following are true about the length of the Sprint? (Choose two.)A . The length of the Sprint should be proportional to the work that is done in between Sprints.B . It is best to have Sprints of consistent length throughout a development effort.C . Sprint length is...

January 18, 2021 No Comments READ MORE +

Which two things should the Development Team do during the first Sprint? (Choose two.)

Which two things should the Development Team do during the first Sprint? (Choose two.)A . Make up a plan for the rest of the project.B . Analyze, describe, and document the requirements for the subsequent Sprints.C . Develop at least one piece of functionality.D . Analyze, design, and describe the...

January 18, 2021 No Comments READ MORE +

Which of the following two actions should the Scrum Master support?

In the Sprint Planning meeting, the Product Owner and the Development Team were unable to reach a clear understanding about the highest order Product Backlog items. Because of this, the Development Team couldn’t figure out how many Product Backlog items it could forecast for the upcoming Sprint. They were able...

January 18, 2021 No Comments READ MORE +

Which three phrases best describe the purpose of a definition of “Done”?

A Development Team selects a set of Product Backlog items for a Sprint Backlog with the intent to get the selected items “Done” by the end of the Sprint. Which three phrases best describe the purpose of a definition of “Done”? (Choose three.)A . It controls whether the developers have...

January 18, 2021 No Comments READ MORE +

When is it most appropriate for a Development Team to change the definition of “Done”?

When is it most appropriate for a Development Team to change the definition of “Done”?A . During Spring Planning.B . Prior to starting a new Sprint.C . During the Sprint Retrospective.D . Prior to starting a new project.View AnswerAnswer: C

January 17, 2021 No Comments READ MORE +

Who should make sure everyone on the Development Team does his or her tasks for the Sprint?

Who should make sure everyone on the Development Team does his or her tasks for the Sprint?A . The Project Manager.B . The Product Owner.C . The Scrum Master.D . The Development Team.E . All of the above.View AnswerAnswer: D

January 17, 2021 No Comments READ MORE +

During a Sprint Retrospective, for what is the Product Owner responsible?

During a Sprint Retrospective, for what is the Product Owner responsible?A . Participating as a Scrum Team member.B . Summarizing and reporting the discussions to the stakeholders that he/she represents in the Scrum Team.C . Capturing requirements for the Product Backlog.D . The Product Owner should not take part in...

January 16, 2021 No Comments READ MORE +

What are three ways Scrum promotes self-organization? (Choose three.)

What are three ways Scrum promotes self-organization? (Choose three.)A . By not allowing documentation.B . By the Development Team deciding what work to do in a Sprint.C . By preventing stakeholders from entering the development room.D . By removing titles for Development Team members.E . By being a lightweight framework.View...

January 16, 2021 No Comments READ MORE +

When can a Development Team cancel a Sprint?

When can a Development Team cancel a Sprint?A . It can’t. Only Product Owners can cancel Sprints.B . When functional expectations are not well understood.C . When the Product Owner is absent too often.D . When the selected Product Backlog items for the Sprint become unachievable.E . When a technical...

January 16, 2021 No Comments READ MORE +