Which of the following metrics will likely be reviewed by at the Daily Scrum for a Scrum Team using Kanban? (choose the best two answers)
Which of the following metrics will likely be reviewed by at the Daily Scrum for a Scrum Team using Kanban? (choose the best two answers)A . Work Age Item. B. Velocity. C. Cycle Time. D. Throughput. E. Work in Progress (WIP). F. Lead Time.View AnswerAnswer: A,E Explanation: The Daily Scrum...
True or False: Batch size is the same as the Sprint length when using Scrum with Kanban.
True or False: Batch size is the same as the Sprint length when using Scrum with Kanban.A . True B. FalseView AnswerAnswer: B Explanation: Each activity in the Scrum Team’s Definition of Workflow can have its own batch size. For example, the team might deploy each Product Backlog item and...
A Kanban board is comprised of which of the following policies? (choose the best two answers)
A Kanban board is comprised of which of the following policies? (choose the best two answers)A . Each Product Backlog Item type has a separate swim lane. B. Your workflow visualization. C. Work in Progress (WIP) Limits. D. Class of service policy.View AnswerAnswer: B,C Explanation: Visualization using the Kanban board...
When using Kanban in Scrum, a team needs to use which of the following four metrics of flow? (choose the best four answers)
When using Kanban in Scrum, a team needs to use which of the following four metrics of flow? (choose the best four answers)A . Cycle Time B. Work in Progress (WIP) C. Work Item Age D. Cumulative Flow Diagram (CFD) E. Lead Time F. ThroughputView AnswerAnswer: A,B,C,F Explanation: The four...
Which of the following are considered leading indicator metrics? (choose the best two answers)
Which of the following are considered leading indicator metrics? (choose the best two answers)A . An item's Work Item Age. B. Service Level Expectation policy. C. Current Work in Progress. D. An item's Cycle Time. E. Monte Carlo simulations.View AnswerAnswer: A,C Explanation: Work Item Age and current WIP are a...
Which is the best description of probabilistic forecast? (choose the best answer)
Which is the best description of probabilistic forecast? (choose the best answer)A . A forecast based on empirical data as an input on the likelihood of achieving a goal given certain time period. B. A formula that calculates a team's future performance. C. A commitment of when a specific scope...
True or False: The purpose of a Scrum Team's Service Level Expectation (SLE) is to allow teams to give each Product Backlog item a commitment to a due date as part of Sprint Planning.
True or False: The purpose of a Scrum Team's Service Level Expectation (SLE) is to allow teams to give each Product Backlog item a commitment to a due date as part of Sprint Planning.A . True B. FalseView AnswerAnswer: B Explanation: The SLE is primarily an internal metric to help...
True or False: In a flow-based system, the number of tasks is not necessarily limited, rather the amount of value-generating work items is limited.
True or False: In a flow-based system, the number of tasks is not necessarily limited, rather the amount of value-generating work items is limited.A . True B. FalseView AnswerAnswer: A Explanation: Even though multiple tasks are completed, none of them has created something of value for the customer. Our goal...
Which of the following is TRUE about the relationship between Sprints and Kanban for Scrum? (choose the best three answers)
Which of the following is TRUE about the relationship between Sprints and Kanban for Scrum? (choose the best three answers)A . Sprints are examples of cycles and cadence. B. Sprints are examples of a policy that shows the team's way of working. C. It is easier to achieve Sprint objectives...
Kanban can help enhance visibility for: (choose the best three answers)
Kanban can help enhance visibility for: (choose the best three answers)A . The Definition of Done. B. The Sprint Backlog. C. The Product Backlog. D. The Sprint Retrospective.View AnswerAnswer: A,B,C Explanation: One of the keys to effective visualization for a Scrum Team is to make sure it sees the flow...