Who is accountable for the Definition of Workflow for the Sprint Backlog? (Choose the best answer)
Who is accountable for the Definition of Workflow for the Sprint Backlog? (Choose the best answer)A . The Developers. B. The Product Owner. C. The Scrum Team. D. The Scrum Master.View AnswerAnswer: A Explanation: As the Developers have autonomy to determine how they turn the Sprint Backlog into an Increment,...
How does setting limits to Work in Progress (WIP) policies support self-management? (choose the best two answers)
How does setting limits to Work in Progress (WIP) policies support self-management? (choose the best two answers)A . WIP Limits creates a boundary for which the Scrum Team self-manages within. B. WIP Limits inhibit self-management since they limit the team's autonomy to pull work. C. As part of self-management Scrum...
What are desired benefits of applying Kanban practices in a Scrum Team? (choose the best four answers)
What are desired benefits of applying Kanban practices in a Scrum Team? (choose the best four answers)A . Increased collaboration between the Developers. B. Scrum Teams are no longer limited by Sprint time-boxes. C. For a work item, the average cycle time may be reduced. D. Increased transparency on the...
What can occur if you were to reduce batch sizes? (Choose all that apply)
What can occur if you were to reduce batch sizes? (Choose all that apply)A . Improved efficiency due to faster feedback loops. B. Higher motivation due to seeing your work get done and deliver value earlier. C. Lower efficiency due to overhead / transaction costs in case the batch size...
True or False: Cycle Time is a lagging indicator.
True or False: Cycle Time is a lagging indicator.A . True B. FalseView AnswerAnswer: A Explanation: You can only measure Cycle Time by looking at historical data. It is an indicator and point of reference but should be used carefully when creating a forecast.
The team needs to work on a high priority urgent unplanned item, but they are at their WIP limit.
The team needs to work on a high priority urgent unplanned item, but they are at their WIP limit. True or False: They should change the WIP limit at their Daily Scrum to enable them to pull in that item. B. True C. FalseView AnswerAnswer: C Explanation: If they do...
True or False: The WIP Limit can only be changed during the Sprint Retrospective.
True or False: The WIP Limit can only be changed during the Sprint Retrospective.A . True B. FalseView AnswerAnswer: B Explanation: While the Sprint Retrospective is indeed the recommended time to inspect and adapt the Workflow, any Workflow policy, including WIP limits, can be changed at any point. There are...
True or False: Scrum Events, Scrum Team Accountabilities, and Scrum Artifacts are changed when using Scrum with Kanban. For example, the Scrum Team might choose to omit the Sprint Retrospective when using Kanban with Scrum.
True or False: Scrum Events, Scrum Team Accountabilities, and Scrum Artifacts are changed when using Scrum with Kanban. For example, the Scrum Team might choose to omit the Sprint Retrospective when using Kanban with Scrum.A . True B. FalseView AnswerAnswer: B Explanation: Adding Kanban to Scrum provides a technique to...
True or False: A Service Level Expectation (SLE) target reflects the Scrum Team’s aspirations toward a reliable cycle time.
True or False: A Service Level Expectation (SLE) target reflects the Scrum Team’s aspirations toward a reliable cycle time.A . True B. FalseView AnswerAnswer: A Explanation: Regardless of whether it is based on historical data or not, a Service Level Expectation (SLE) indeed is an expectation the team sets for...
Which of the following best describes Kanban? (choose the best answer)
Which of the following best describes Kanban? (choose the best answer)A . Additional practices that are integrated into the Scrum framework. B. A strategy for optimizing the flow of value through a process that uses a visual, Work in Progress (WIP) limited pull system. C. A process of defining a...