Scrum requires that the Product Owner must use which of the following items? (Choose all that apply)
Scrum requires that the Product Owner must use which of the following items? (Choose all that apply)
A . Burndown chart.
B . Feature bum-up.
C . Critical Path Analysis.
D . Project Gantt chart.
E . None of the above.
Answer: E