Which of the following can influence how items are ordered in the Product Backlog? (Choose all that apply)
- A . The value of Product Backlog items.
- B . Dependencies between Product Backlog items.
- C . External dependencies.
- D . Cost of delay.
- E . Cost to implement.
As a Product Owner, which of the following would help you minimize waste in managing the Product Backlog? (Choose the best two answers)
- A . Have the Business Analyst manage the Product Backlog.
- B . Ensure that the Product Backlog items include detailed description of the technical solutions.
- C . Ensure that Product Backlog items are written in a clear and unambiguous way.
- D . Only fully describe Product Backlog items when they are likely soon to be worked on.
What are appropriate responses if the Scrum Team identifies that the workload in the Sprint Backlog has become greater than their capacity during the Sprint Planning? (Choose the best two answers)
- A . The Scrum Team members ensure that the Product Owner is aware, starts the Sprint and monitors progress.
- B . Start the Sprint and add additional resources to the Scrum Team.
- C . Remove, replace, or make changes to selected Product Backlog items in the Sprint Backlog.
- D . Budget overtime in order to meet the commitment.
- E . Look for another team that has free capacity to take on the extra work.
Which statement best describes the Sprint Review? (Choose the best answer)
- A . An inspection of all of the work done in the Sprint by the Developers.
- B . An opportunity for the Scrum Team and stakeholders to inspect the Increment and collaborate on the next steps.
- C . A demonstration of functionality completed in the Sprint.
- D . An opportunity for the Product Owner to evaluate the results of the Developers.
A Scrum Team must have a Product Owner and Scrum Master.
True or False:
- A . True. Each must be a full-time member on the Scrum Team.
- B . False. If a Product Owner is unavailable, he/she can be replaced by a Business Analyst.
- C . False. A Scrum Master is only necessary when requested or needed.
- D . True. Their participation and availability will impact the outcomes produced by the Scrum Team.
How much time is allowed between the conclusion of the current Sprint and the start of the next Sprint? (Choose the best answer)
- A . Enough time for the Product Owner to prepare the Product Backlog for Sprint Planning.
- B . Enough time for the last Increment to finish testing.
- C . All of the above are allowed.
- D . None. A new Sprint starts immediately following the conclusion of the previous Sprint.
- E . Maximum of 1 day for Sprints that are time-boxed to 2 weeks.
What can be an indication that the Product Owner is not spending enough time with the Scrum Team? (Choose the best answer)
- A . He is not with the Scrum Team full time.
- B . The velocity is dropping.
- C . He is surprised by what was delivered in the Increment at the Sprint Review.
- D . The burn down chart is not being kept up to date.
When should the Product Backlog be updated? (Choose the best answer)
- A . During the Sprint Retrospective.
- B . Before the first Sprint starts.
- C . When the Product Owner has time.
- D . Before each Sprint Planning to know which items to commit to the upcoming Sprint.
- E . As new information and insights emerge.
In the context of Scrum, which of the following are considered feedback loops? (Choose all that apply)
- A . Daily Scrum
- B . Sprint Retrospective
- C . Sprint Review
- D . Release planning
The Product Owner role: (Choose the best three answers)
- A . Can be influenced by a committee.
- B . Can be represented by a committee or a team of people.
- C . Is one person.
- D . Is accountable for the Product Backlog’s flow of value.