When determining the ordering of an item on the Product Backlog, what are some things a Product Owner should consider? (choose all that apply)
- A . Alignment with business strategy and goals
- B . Importance to customers
- C . The complexity of developing the Product Backlog Item
- D . Risk
- E . Alignment and dependencies with existing Product Backlog items
A,B,C,D,E
Explanation:
All of them are correct.
WHY ORDERING YOUR BACKLOG IS IMPORTANT
There are many reasons why having a healthy, ordered product backlog is important to teams.
Your organization uses NPS (Net Promoter Score) measures to understand your customers’ satisfaction levels. Your team had invested a lot of time and effort creating and delivering a release that included many new product features. After a few months, you see that the NPS score did not improve.
What other measures can help you to better understand this outcome? (choose the best two answers)
- A . Market Share
- B . Lead Time
- C . Release Frequency
- D . Installed Version
- E . Feature Usage Index
B,E
Explanation:
Feature Usage Index helps to measure usage, by feature, to help infer the degree to which customers find the product useful and whether actual usage meets expectations on how long users should be taking with a feature.
Lead Time is the amount of time from when an idea is proposed, or a hypothesis is formed until a customer can benefit from that idea. This measure may vary based on customer and product. It is a contributing factor to customer satisfaction.
Dereck is new to the Product Owner role and is asking you for advice on what he should be doing to be an effective Product Owner.
Which of the following would be the most appropriate advice to give him? (choose the best answer)
- A . Be the only point of contact for all stakeholders.
- B . Have an understanding of all items in the Product Backlog to the level needed to maximize the flow of value.
- C . Maximize the productivity of the team.
- D . None of the above.
- E . Ensure that all of the stakeholder needs are met.
- F . All of the above.
B
Explanation:
The Product Owner is accountable for maximizing the value of the product resulting from the work of the Scrum Team
The Product Owner’s decisions are visible in the content and ordering of the Product Backlog. The Decision Maker, one of the preferred stances of a Product Owner, helps the stakeholders and Scrum Team to keep time-to-market short, by keeping decision making time short. Therefore, he/she must have an "expert" opinion on the items in the Product Backlog in order to fulfill his role.