When the Developers determine that they will not be able to finish the complete forecast, who has to be present when reviewing and adjusting the Sprint work selected? (choose the best answer)
- A . The Product Owner and all stakeholders.
- B . The Scrum Master and the Developers.
- C . The Scrum Master, project manager and the Developers
- D . The Product Owner and the Developers.
True or False: An Increment must be released to customers or users at the end of each Sprint.
- A . TRUE
- B . FALSE
A Product Backlog is: (Choose the best three answers)
- A . Ordered based on priority, value, dependencies, and risk.
- B . Only visible to the Product Owner and stakeholders.
- C . An inventory of things to be done for the Product.
- D . An exaustive list of upfront approved requirements to be implemented.
- E . Managed by the Product Owner.
True or False: To g et started in terms of what to build, Scrum requires no more than à Product “Owner with enough ideas for a first Sprint, Developers to implement those ideas, and a Scrum Master to help guide the process.
- A . TRUE
- B . FALSE
Why does the Product Owner want the Developers to adhere to its Definition of Done? (Choose the best answer)
- A . To be able to reprimand the team when they do not meet their velocity goal for the Sprint.
- B . To predict the team’s productivity over time.
- C . To have complete transparency into what has been done at the end of each Sprint.
- D . To know what the team will deliver over the next three Sprints.
Which statement best describes the Sprint Backlog as the output of the Sprint Planning? (Choose the best answer)
- A . Every item has a designated owner.
- B . It is ordered by the Product Owner.
- C . Each task is estimated in hours.
- D . It is the Developers plan for the Sprint.
- E . It is a complete list of all work to be done in a Sprint.
Which is NOT a valid consideration when ordering a Product Backlog? (Choose the best answer)
- A . Importance to customers.
- B . Tools and techniques,
- C . Alignment with business strategy and goals.
- D . Risk.
- E . Dependencies on other Product Backlog items.
True or False: Product Owners must specify complete acceptance criteria for a Product Backlog item before the Developers can select the item in Sprint Planning.
- A . TRUE
- B . FALSE
A Product Owner is accountable for maximizing the value of the product that is the result of the Work of the Scrum Team.
Which of the following can be delegated to others, while the Product Owner remains accountable for the work? (Choose the best two answers)
- A . Attending the Sprint Retrospective
- B . Attending the Sprint Review.
- C . Ordering Product Backlog items.
- D . Developing and communicating the Product Goal.
True or False: All planned work for the Product done by the Scrum Team must originate from the Product Backlog.
- A . TRUE
- B . FALSE