During a Sprint, when is new work or further decomposition of work added to the Sprint Backlog?
- A . When the Product Owner identifies new work.
- B . As soon as possible after they are identified.
- C . When the Scrum Master has time to enter them.
- D . During the Daily Scrum after the Development Team approves them.
What it the main reason for the Scrum Master to be at the Daily Scrum?
- A . To gather status and progress information to report to management.
- B . To write down any changes to the Sprint Backlog, including adding new items, and tracking progress on the burn-down.
- C . He or she does not have to be there; he or she only has to ensure the Development Team has a Daily Scrum.
- D . To make sure every team member answers the three questions.
You have six teams using a traditional method to deliver a product. Your management has asked you to start using Scrum. In the initial project there were separate plans and teams for the layers of a software system, i.e. one for the front-end, one for the middle tier, one for the back-end, and one for the interfaces and services. This resembles what is known as component teams. But you have read that it’s a good idea to have teams organized by feature.
What are the advantages of keeping component teams while starting Scrum?
- A . There’s less initial disruption than organizing into new teams. As they start, they will discover what works best, and how to potentially re-organize towards this.
- B . Component teams generally have the skills needed to create a working Increment of software that provides business value.
- C . Because they have worked together for some time, they are likely able to start producing shippable Increments faster that new feature teams would.
- D . There are fewer cross-team dependencies than working in feature teams.
How should Product Backlog items be chosen when multiple Scrum Teams work from the same Product Backlog?
- A . The Scrum Team with the highest velocity pulls Product Backlog items first.
- B . The Development Teams pull in work in agreement with the Product Owner.
- C . The Product Owner should provide each team with its own Product Backlog.
- D . Each Scrum Team takes an equal numbers of items.
- E . The Product Owner decides.
How often should Development Team membership change?
- A . As needed, while taking into account a short term reduction in productivity.
- B . Never, because it reduces productivity.
- C . As needed, with no special allowance for changes in productivity.
- D . Every Sprint to promote shared learning.
Who should make sure everyone on the Development Team does their tasks for the Sprint?
- A . The Project Manager.
- B . The Product Owner.
- C . The Scrum Master.
- D . The Development Team.
- E . All of the above.
When is it most appropriate for a Development Team to change the definition of “Done”?
- A . During Spring Planning.
- B . Prior to starting a new Sprint.
- C . During the Sprint Retrospective.
- D . Prior to starting a new project.
The Daily Scrum is an event that happens every day.
What would be three key concerns if the frequency were to be lowered to every two or three days? (Choose three.)
- A . Opportunities to insect and adapt the Sprint Backlog are lost.
- B . Impediments are raised and resolved more slowly.
- C . The Product Owner cannot accurately report progress to the stakeholders.
- D . Too much work is spent updating the Scrum board before the meeting.
- E . The Scrum Master loses the ability to update the Gantt chart properly.
- F . The Sprint plan may become inaccurate.
Which statement best describes Scrum?
- A . A defined and predictive process that confirms to the principles of Scientific Management.
- B . A complete methodology that defines how to develop software.
- C . A cookbook that defines best practices for software development.
- D . A framework within which complex products in complex environments are developed.
Which Scrum Values are exhibited by not building Product Backlog items that have low business value? (Choose three.)
- A . Economic Value Added.
- B . Respect.
- C . Focus.
- D . Earned Value.
- E . Courage.
63, 123: sprint goal
Qestions 63 and 123: Which output from Sprint Planning provides the Development Team with a target and overarching direction for the Sprint?
Answer to 63: Sprint Backlog
Answer to 123: Sprint Goal
Same question, different answers. Which answer is correct?
Hi, there is an issue in #67, please review:
67. What are two good ways for the Development Team to make non-functional requirements visible? (Choose two.)
1 Put them on a separate list on the Scrum board, available for all to see.correct
2 Add them to the Product Backlog and keep the Product Owner posted on the expected effort.correct
3 Run the integration and regression tests before the end of the Sprint, and capture the open work for the Sprint Backlog of the next Sprint.wrong
4 Add them to the definition of “Done” so the work is taken care of every Sprint.
I`ve chosen last two, but is says that #3 is incorrect. Then what 2 answers are correct?
Thanks!
bbbbb