What is the key concern when multiple Development Teams are working from the same Product Backlog?
- A . Minimizing dependencies between teams.
- B . Clear definition of requirements.
- C . Meeting original scope projections.
- D . Making sure there’s enough work for everyone on every team.
- E . Maximizing velocity.
What does it mean to say that an event has a time-box?
- A . The event must happen at a set time.
- B . The event must happen by a given time.
- C . The event must take at least a minimum amount of time.
- D . The event can take no more than a maximum amount of time.
Which outcome is expected as Scrum Teams mature?
- A . They will improve their definition of “Done” to include more stringent criteria.
- B . The Sprint Retrospectives will grow to be longer than 4 hours.
- C . There is no need for a time-boxed Sprint, since time-boxes are only for new Scrum Teams.
- D . Sprint Reviews will no longer be needed.
- E . A Scrum Master is no longer needed since they are a mature team now.
The Product Owner must release each Increment to production.
- A . When it makes sense.
- B . To make sure the Development Team is done every Sprint.
- C . Whenever the product is free of defects.
- D . Without exception.
A properly functioning Scrum Team will have at least one Release Sprint and may well have several.
- A . True
- B . False
Scrum is a methodology that tells in detail how to build software incrementally.
- A . True
- B . False
For which is the Scrum Master responsible?
- A . Managing the performance of the Scrum Team.
- B . The meetings and the objectives that a Scrum Team sets for itself.
- C . The Scrum framework being adopted and used properly.
- D . Keeping track of resource allocation.
A Development Team asks their Product Owner to re-order the Product Backlog. The team is waiting for an external supplier to deliver a specific software component. Without that component there won’t be enough work in the next Sprint to occupy the full team. The Product Owner asks the Scrum Master for help.
What would be good advice to give the Product Owner?
- A . Remind the Product Owner that his primary concern is the flow of value reflected in the ordering of the Product Backlog.
- B . Tell the Product Owner to re-order the Product Backlog so the work involving the external component can be planned in a separate sprint.
- C . Tell the Product Owner that the Product Backlog should be ordered to maximize utilization of the Development Team.
As the Sprint Planning meeting progresses, the Development Team sees that the workload is greater than they can handle.
Which two are valid actions? (Choose two.)
- A . Recruit additional Development Team members before the work can begin.
- B . The Development Team ensures that the Product Owner is aware, starts the Sprint, and monitors progress.
- C . Cancel the Sprint.
- D . Remove or change selected Product Backlog items.
- E . The Development Team works overtime during this Sprint.
Currently, your Development Teams are organized to address a single layer only (for example, front end, middle tier, back end, and interfaces).
What are three things to consider when deciding to move away from such component teams toward feature teams? (Choose three.)
- A . You cannot do Scrum without feature teams.
- B . Productivity may suffer when making this kind of move.
- C . Getting support from the business side first helps.
- D . Feature teams have less communication overhead.
- E . With feature teams, it is easier to calculate the productivity per team.
63, 123: sprint goal
Qestions 63 and 123: Which output from Sprint Planning provides the Development Team with a target and overarching direction for the Sprint?
Answer to 63: Sprint Backlog
Answer to 123: Sprint Goal
Same question, different answers. Which answer is correct?
Hi, there is an issue in #67, please review:
67. What are two good ways for the Development Team to make non-functional requirements visible? (Choose two.)
1 Put them on a separate list on the Scrum board, available for all to see.correct
2 Add them to the Product Backlog and keep the Product Owner posted on the expected effort.correct
3 Run the integration and regression tests before the end of the Sprint, and capture the open work for the Sprint Backlog of the next Sprint.wrong
4 Add them to the definition of “Done” so the work is taken care of every Sprint.
I`ve chosen last two, but is says that #3 is incorrect. Then what 2 answers are correct?
Thanks!