Which of the following is required by Scrum? (Choose all that apply.)
- A . Sprint Retrospective.
- B . Members must be stand up at the Daily Scrum.
- C . Sprint Burndown Chart.
- D . Release planning.
- E . All of the above.
What is the purpose of a Sprint Review?
- A . To take time to judge the validity of the project.
- B . To inspect the product increment with the stakeholders and collect feedback on next steps.
- C . To review the Scrum Team’s activities and processes during the Sprint.
- D . To build team sprint.
Who determines when it is appropriate to update the Sprint Backlog during a Sprint?
- A . The Scrum Team.
- B . The Product Owner.
- C . The Developers.
- D . The Project Manager.
Who must attend the Daily Scrum?
- A . The Scrum Master and Product Owner.
- B . The Development Team.
- C . The Development Team and Product Owner.
- D . The Scrum Team.
- E . The Development Team and Scrum Master.
When do Development Team members take ownership of a Sprint Backlog item?
- A . At the Sprint planning meeting.
- B . During the Daily Scrum.
- C . Never. All Sprint Backlog Items are “owned” by the entire Development Team, even though each one may be done by an individual Development Team member.
- D . Whenever a team member can accommodate more work.
The purpose of a Sprint is to produce a done Increment of product.
- A . True
- B . False
Who creates the definition of “Done”?
- A . The Scrum Master as he/she is responsible for the Development Team’s productivity.
- B . The Scrum Team, in a collaborative effort where the result is the common denominator of all members’ definition.
- C . The Product Owner as he/she is responsible for the product’s success.
- D . The development organization (or Development Team if none is available from the development organization).
Five new Scrum Teams have been created to build one product. A few of the developers on one of the Development Teams ask the Scrum Master how to coordinate their work with the order teams.
What should the Scrum Master do?
- A . Teach the Product Owner to work with the lead developers on ordering Product Backlog in a way to avoid too much technical and development overlap during a Sprint.
- B . Teach them that it is their responsibility to work with the other teams to create an integrated Increment.
- C . Collect the Sprint tasks from the teams at the end of their Sprint Planning and merge that into a consolidated plan for the entire Sprint.
- D . Visit the five teams each day to inspect that their Sprint Backlogs are aligned.
Which two things should the Development Team do during the first Sprint? (Choose two.)
- A . Make up a plan for the rest of the project.
- B . Analyze, describe, and document the requirements for the subsequent Sprints.
- C . Develop at least one piece of functionality.
- D . Analyze, design, and describe the complete architecture and infrastructure.
- E . Create an increment of potentially releasable software.
What are three ways Scrum promotes self-organization? (Choose three.)
- A . By not allowing documentation.
- B . By the Development Team deciding what work to do in a Sprint.
- C . By preventing stakeholders from entering the development room.
- D . By removing titles for Development Team members.
- E . By being a lightweight framework.
63, 123: sprint goal
Qestions 63 and 123: Which output from Sprint Planning provides the Development Team with a target and overarching direction for the Sprint?
Answer to 63: Sprint Backlog
Answer to 123: Sprint Goal
Same question, different answers. Which answer is correct?
Hi, there is an issue in #67, please review:
67. What are two good ways for the Development Team to make non-functional requirements visible? (Choose two.)
1 Put them on a separate list on the Scrum board, available for all to see.correct
2 Add them to the Product Backlog and keep the Product Owner posted on the expected effort.correct
3 Run the integration and regression tests before the end of the Sprint, and capture the open work for the Sprint Backlog of the next Sprint.wrong
4 Add them to the definition of “Done” so the work is taken care of every Sprint.
I`ve chosen last two, but is says that #3 is incorrect. Then what 2 answers are correct?
Thanks!
bbbbb