Scrum Masters have to solve both internal and external impediments for the Scrum team during the Create Deliverables process. To do so, they record the impediments in the Impediment Log during _________________________.

Scrum Masters have to solve both internal and external impediments for the Scrum team during the Create Deliverables process. To do so, they record the impediments in the Impediment Log during _________________________.

A) Daily Standup Meetings.

B) Sprint Review Meetings.

C) Release Planning Meetings.

D) Sprint Planning Meetings.
A . A and В
B . A
C . A and D
D . A, B, and C

Answer: A

Explanation:

Reference: http://www.cs.vsu.ru/~svv/spm/SBOK_Guide_3rd_edition_English_Sample.pdf (45)