Scrum addresses which of the following four risks in software development? (Choose four.)
A . The complexity and unpredictability of the requirements.
B . The stability and complexity of the technology.
C . The skills and working relationships of the people on the teams.
D . The timescale of the planned work.
E . The clear definitions of stages and gateways in the overall governance model.
F . The definition of incentive and bonus strategies by HR for all team members.
Answer: ABCD
Explanation:
Scrum is a framework within which people can address complex adaptive problems, while productively and creatively developing, delivering, and sustaining complex products of the highest possible value. Scrum employs an iterative, incremental approach to optimize predictability and control risk.