(Select 2) Why is Architectural Runway important?
(Select 2) Why is Architectural Runway important?A . It supports a stable velocity.B . It provides the documentation on which Features and Capabilities are built.C . It iteratively evolves the architecture to meet changing needs.D . It allows for nontechnical changesView AnswerAnswer: A, C
(Select 2) What are the responsibilities of a Business Owner?
(Select 2) What are the responsibilities of a Business Owner?A . Assign business value to Team Objectives during PI Planning.B . Participate in Post-PI Planning and assist trains in adjusting ART PI plans as needed.C . Assign business value to Epics and Features.D . Ensure that the Solution Demo occurs.E...
What would be the best course of action to reduce inconsistencies?
Select 2) You are prioritizing Epics and the group cannot reach a consensus on WSJF parameters. What would be the best course of action to reduce inconsistencies?A . Collect additional input from other stakeholders.B . Take time to provide more detailed specifications for each Epic.C . Use strategic themes to...
ARTs that consist only of Feature teams do not require an Architectural Runway.
ARTs that consist only of Feature teams do not require an Architectural Runway.A . TrueB . FalseView AnswerAnswer: B
What are the primary responsibilities of Program Portfolio Management (PPM)?
What are the primary responsibilities of Program Portfolio Management (PPM)?A . Governance, strategy and investment funding, program management.B . Program management, stakeholder management, PI Planning.C . Lightweight business case, Epic specification workshop, Budget allocation.D . Governance, investment funding, product strategy.View AnswerAnswer: A
If a Value Stream is bigger than the recommended ART size, SAFe recommends splitting it by development process steps and organizing the trains around those steps respectively.
If a Value Stream is bigger than the recommended ART size, SAFe recommends splitting it by development process steps and organizing the trains around those steps respectively.A . TrueB . FalseView AnswerAnswer: B
What is Cost of Delay?
What is Cost of Delay?A . Cost incurred when system integration appears too late in the PI.B . Opportunity cost and deferred revenue.C . Penalty for nonperformance.D . Cost of not addressing risk early on.View AnswerAnswer: A
What role would a traditional program manager most likely take on in SAFe?
What role would a traditional program manager most likely take on in SAFe?A . Release Train Engineer or Value Stream Engineer.B . Scrum masterC . Business OwnerD . Product ManagerView AnswerAnswer: A
What steps in the Portfolio Kanban are most appropriate for running research spikes? (Select 2)
What steps in the Portfolio Kanban are most appropriate for running research spikes? (Select 2)A . Analysis-spikes help clarify feasibility.B . Implementing-teams perform spikes as usualC . Funnel-understand whether the Epic makes sense.D . Portfolio Backlog-run a spike before pulling into development.View AnswerAnswer: A, C
What are stretch objectives?
What are stretch objectives?A . Objectives that are beyond the capacity of the team and so are uncommitted for the PI.B . Objectives that are part of the team's capacity but not necessarily achievable during the PI.C . Objectives that are identified during the PI.D . Objectives that the business...