Which of the following is a key characteristic of the Agile project approach?
Which of the following is a key characteristic of the Agile project approach?A . Formal and detailed documentationB . Frequent and detailed project schedulingC . Iterative build with frequent inspectionsD . Frequesnt quality gatesView AnswerAnswer: C
Which of the following Key Deliverables do you complete in the Solution Design work stream in the Explore phase?
Which of the following Key Deliverables do you complete in the Solution Design work stream in the Explore phase?A . Validation WorkshopsB . Data Migration ApproachC . Design for the Gaps and DeltasD . Baseline BuildE . Solution Scope and Value DeterminationView AnswerAnswer: A,B,C
What is the purpose of a firm-up sprint?
What is the purpose of a firm-up sprint?A . To revise the release plan and sprint planB . To run an end-to-end integration testC . To demonstrate functionality from previous sprintsD . To perform string testView AnswerAnswer: D
Which of the following scenarios are enabled for the "selective data transition" Transition Path with the SAP landscape transformation tool? There are 3 answers to this question.
Which of the following scenarios are enabled for the "selective data transition" Transition Path with the SAP landscape transformation tool? There are 3 answers to this question.A . System consolidationB . Consolidation through online data replicationC . Security migrationD . Extraction of business unitsE . System upgradeView AnswerAnswer: A,B,D
In which phase of the SAP Activate Methodology does the team complete the System Assessment? Please choose the answer.
In which phase of the SAP Activate Methodology does the team complete the System Assessment? Please choose the answer.A . ExploreB . DeployC . PrepareD . RealizeView AnswerAnswer: C
Which criterion does the Product Owner use to sequence the product backlog? Please choose the answer.
Which criterion does the Product Owner use to sequence the product backlog? Please choose the answer.A . ComplexityB . Relative effortC . Resource availabilityD . Business priorityView AnswerAnswer: D
In which phase do you verify that the SAP Best Practices content meets the customer's business needs, and then capture gaps?
In which phase do you verify that the SAP Best Practices content meets the customer's business needs, and then capture gaps?A . ExploreB . DeployC . RealizeD . PrepareView AnswerAnswer: A
What does "de-coupling extensions" mean in SAP S/4HANA Cloud?
What does "de-coupling extensions" mean in SAP S/4HANA Cloud?A . Extensions could conflict with future release enhancementsB . Extensions are applied with modifications in the HANA databaseC . Extensions will not clash with quarterly release upgradesD . Extensions are separated from the stable system of recordsView AnswerAnswer: D
What are some core objectives of business process monitoring? 2 correct answers
What are some core objectives of business process monitoring? 2 correct answersA . to provide transparency over end-to-end processesB . to provide process update and change feedbackC . to provide reverse business process analysisD . to increase business process execution qualityView AnswerAnswer: A,D
What is the difference between the "system conversion" and the "new implementation OF SAP S/4HANA transaction path. There are 2 option to this question.
What is the difference between the "system conversion" and the "new implementation OF SAP S/4HANA transaction path. There are 2 option to this question.A . In the realize phase, data is converted and not migrated for system conversionB . There are different upgrade cyclesC . In the realize phase, custom...