Which planning procedure do you use to create a feasible production plan from a requirements planning perspective?
When analyzing the SAP ECC order report for a planned order for a finished product, you discover that one of the assemblies will not be available in time for the scheduled final assembly because of automatic forward scheduling. Which planning procedure do you use to create a feasible production plan...
Where can you define the valid receivers for production order costs?
Where can you define the valid receivers for production order costs?A . In the costing variantB . In the settlement profileC . In the valuation variantD . In the production scheduling profileView AnswerAnswer: B
Where can you define the valid receivers for production order costs?
Where can you define the valid receivers for production order costs?A . In the costing variantB . In the settlement profileC . In the valuation variantD . In the production scheduling profileView AnswerAnswer: B
Which of the following features are offered by MRP areas in SAP ECC? (Choose two)
Which of the following features are offered by MRP areas in SAP ECC? (Choose two)A . A storage location may be assigned to different MRP areas.B . An MRP area may include different storage locations.C . Make-to-order production is supported by storage location MRP areas.D . Subcontracting is supported by...
What is the correct sequence of the planning procedures?
You want to use the different options for planning in SAP ECC. What is the correct sequence of the planning procedures?A . Sales and operations planning -> Demand management -> Long-term planning -> Material requirements planning -> Capacity planningB . Demand management -> Sales and operations planning -> Capacity planning...
Where can you define the valid receivers for production order costs?
Where can you define the valid receivers for production order costs?A . In the costing variantB . In the settlement profileC . In the valuation variantD . In the production scheduling profileView AnswerAnswer: B
What features related to process orders can be used to fulfill Good Manufacturing Practices (GMP) requirements? (Choose three)
What features related to process orders can be used to fulfill Good Manufacturing Practices (GMP) requirements? (Choose three)A . Approved master recipesB . Digital signatureC . Electronic batch recordD . Availability checkE . Resource selectionView AnswerAnswer: A,B,C
What do you have to consider for the two lists at this stage?
A material was planned in the context of SAP ECC material requirements planning. The MRP controller subsequently processed the material by manually converting a specific planned order into a production order. The MRP controller now accesses the current stock/requirements list and the MRP list for this material and compares these...
Where can you define the valid receivers for production order costs?
Where can you define the valid receivers for production order costs?A . In the costing variantB . In the settlement profileC . In the valuation variantD . In the production scheduling profileView AnswerAnswer: B
What are the consequences of setting a production order to Technically Complete (TECO)? (Choose three)
What are the consequences of setting a production order to Technically Complete (TECO)? (Choose three)A . The order is no longer relevant for material requirements planning.B . Capacity requirements are set to null.C . Confirmations are no longer possible.D . Reservations are no longer relevant for material requirements planning.E ....