On which document in the sales process is the profit initially entered?

On which document in the sales process is the profit initially entered?A . Sales inquiryB . Sales orderC . Goods issueD . Service contractView AnswerAnswer: B

July 13, 2021 No Comments READ MORE +

How do you do this?

You want to determine which operations of the oruting should be considered in a product cost calculation . How do you do this? 2 AnswersA . By marking the cost indicator in the control key assigned to the operationB . By assigning a cost center top the work center in...

July 12, 2021 No Comments READ MORE +

Which parameters are controlled by the costing type in a costing variant? 2 answers

Which parameters are controlled by the costing type in a costing variant? 2 answersA . Price for materialsB . Price updateC . Save with date keyD . Costing sheetView AnswerAnswer: B,C

July 11, 2021 No Comments READ MORE +

How do you maintain number intervals/ranges in Controlling?

How do you maintain number intervals/ranges in Controlling?A . By posting keyB . By business transactionC . By company codeD . By document typeView AnswerAnswer: B

July 11, 2021 No Comments READ MORE +

In the product Cost by Order component, what does the system calculate depending on the order status? 1 answer

In the product Cost by Order component, what does the system calculate depending on the order status? 1 answerA . WIP at target costs or variancesB . WIP at actual costs or variancesC . WIP at planned costs or variancesD . Both WIP and variances or only variancesView AnswerAnswer: B

July 11, 2021 No Comments READ MORE +

What are some of the characteristics of Profit Center Accounting in SAp S/4HANA? 2 answers

What are some of the characteristics of Profit Center Accounting in SAp S/4HANA? 2 answersA . It is possible to derive the profit center from the segment in configurationB . It is integrated in the universal journalC . It can be used in the settlement rule for internal ordersD ....

July 10, 2021 No Comments READ MORE +

In a standard system delivery, how many characteristics can be added to an operating concern?

In a standard system delivery, how many characteristics can be added to an operating concern?A . Over 150B . 101-150C . 0-70D . 71-100View AnswerAnswer: C

July 10, 2021 No Comments READ MORE +

How can you define a dynamic group for internal orders?

How can you define a dynamic group for internal orders?A . Use wild cards in the order codes assigned to nodesB . Assign a selection variant to an end nodeC . Define an order coding mask for order typesD . Create a substitution rule for mass changesView AnswerAnswer: A

July 10, 2021 1 Comment READ MORE +

Which cost estimates must you reuse with the transfer control functionality?

Which cost estimates must you reuse with the transfer control functionality?A . Cost estimates across company codesB . Cost estimates with same cost component structureC . Cost estimates with quantity structureD . Cost estimates within the same plantView AnswerAnswer: B

July 10, 2021 No Comments READ MORE +

What can you use to difference two or more cost estimates for the same material? 2 answers

What can you use to difference two or more cost estimates for the same material? 2 answersA . Valuation variantB . Transfer controlC . Costing variantD . Costing versionView AnswerAnswer: C,D

July 10, 2021 No Comments READ MORE +