How can you process consumption postings?

In a production process, you need acertain amount of liquid as input material. The source tank is directly connected to the reactor . How can you process consumption postings?A . KanbanB . Picking listC . BackflushingD . Transfer OrderView AnswerAnswer: B

August 19, 2021 1 Comment READ MORE +

For a production version to be valid and consistent what requirements must be fulfilled?

For a production version to be valid and consistent what requirements must be fulfilled? Note: There are 3 correct answers to this question.A . The lot size range must be within the lot-size range of the assigned routing.B . The assigned routing must be a rate routing.C . The deletion...

August 19, 2021 No Comments READ MORE +

Which planning procedure do you recommend?

You want to reduce planning efforts for B/C materials . Which planning procedure do you recommend?A . Manual planning without checkB . Forecast planningC . Material requirements planningD . Consumption-based planningView AnswerAnswer: D

August 19, 2021 No Comments READ MORE +

What is the impact of this decision?

Your project team decides to use a make-to-order planning strategy for a strategic material in discrete manufacturing . What is the impact of this decision? Note: There are 3 correct answers to this question.A . Sales order-specific planning run is required.B . Sales order-specific stock is createdC . Net requirements...

August 19, 2021 No Comments READ MORE +

Which options do you have to exclude a material from the MRP run?

In your plant, MRP is activated . Which options do you have to exclude a material from the MRP run? Note: There are 2 correct answers to this question.A . Use a specific material status.B . Use a specific MRP controller.C . Use a specific material groupD . Use a...

August 19, 2021 No Comments READ MORE +

Where do you maintain the duration of a production operation?

Where do you maintain the duration of a production operation?A . Bill of material (BOM)B . Work instructionsC . Material masterD . RoutingView AnswerAnswer: D

August 19, 2021 No Comments READ MORE +

In the Schedule Production app, which settings can you make in the planning strategy? Note: There are 3 correct answers to this question.

In the Schedule Production app, which settings can you make in the planning strategy? Note: There are 3 correct answers to this question.A . Fixed pegging (on/off)B . Planning mode (bucket/sequence)C . Finiteness level (0...1)D . Direction (forward/backward)E . Scheduling control (finite/infinite)View AnswerAnswer: B,D,E

August 19, 2021 No Comments READ MORE +

What is a work center hierarchy in SAP S/4HANA capacity planning?

What is a work center hierarchy in SAP S/4HANA capacity planning?A . A group of alternative work centers for production, structured in hierarchy levels by prior tiesB . A group of work centers in a parallel sequence that is used to split product on quantities and work on them in...

August 18, 2021 No Comments READ MORE +

How does the system choose the product conversion?

Duringproduction order creation, several valid production versions are found . How does the system choose the product conversion?A . Validity period or sales orderB . Lot size or material costC . Alphanumeric or quota arrangementD . Planned order or materialnumberView AnswerAnswer: C

August 18, 2021 No Comments READ MORE +

In which data objects do you maintain the production line as the work center for repetitive manufacturing? Note: There are 2 correct answers to this question.

In which data objects do you maintain the production line as the work center for repetitive manufacturing? Note: There are 2 correct answers to this question.A . Production versionB . Production cost collectorC . RoutingD . Repetitive manufacturing profileView AnswerAnswer: A,C

August 18, 2021 No Comments READ MORE +