What can be determined using the offset within a maintenancestrategy?
What can be determined using the offset within a maintenancestrategy?A . The cycle duration B. The first due date of a maintenance package C. The start date of the maintenance order D. The call date for the maintenance orderView AnswerAnswer: B
Which parameter in the material master is a prerequisite for refurbishment?
Which parameter in the material master is a prerequisite for refurbishment?A . Valuation class 8000 B. Valuation category C (condition-based) C. Valuation type H (origin) D. Valuation category B (in-house/external procurement)View AnswerAnswer: B
A piece of equipment cannot be linked to a material. Determine whether this statement is true or false.
A piece of equipment cannot be linked to a material. Determine whether this statement is true or false.A . True B. FalseView AnswerAnswer: B
What are theeffects?
You cancel the technical completion of a work order. What are theeffects? Note: There are 2 correct answers to this question.A . Open purchase orders are recompiled. B. Open reservations are recompiled. C. Referenced notifications are put In Process again. D. Open purchase requisitions are recompiledView AnswerAnswer: B,D
What do you need to do?
You want to set up a general maintenance task list for inspection rounds using the overall time confirmation as a simplified way torecord measurement documents. What do you need to do? Note: There are 2 correct answers to this question.A . Assign a piece of equipment with an allocated measuring...
Which of the following can you assign to an equipment category via a view profile? Note: There are 2 correct answers to this question.
Which of the following can you assign to an equipment category via a view profile? Note: There are 2 correct answers to this question.A . Configuration B. Manufacturer data C. Serial data D. WarrantyView AnswerAnswer: A,C
Which objects have been enhanced with linear data in maintenance processes? Note:
Which objects have been enhanced with linear data in maintenance processes? Note: There are 3 correct answers to this question.A . Work order confirmation B. Maintenance plan header C. Measurement document D. Maintenance plan item E. Equipment task listView AnswerAnswer: A,C,D
Which parameter do you have to use to map this in the system?
You want to set up a scenario for regular maintenance. The first event should take place after 1 year; after that, it is a regular cycle of 6 months. Which parameter do you have to use to map this in the system?A . Shift factor B. Maintenance plan category C....
Which statements related to the creation of maintenance orders arecorrect? Note: There are 2 correct answers to this question.
Which statements related to the creation of maintenance orders arecorrect? Note: There are 2 correct answers to this question.A . The document within the document management system canbe assigned only at operational level. B. The long text of the reference notification can be automatically copied as the long text of...
Which scheduling parameters are used in a multiple-counter plan? Note: There are 2 correct answers to this question.
Which scheduling parameters are used in a multiple-counter plan? Note: There are 2 correct answers to this question.A . Scheduling period B. Factory calendar C. Start date D. Scheduling indicatorView AnswerAnswer: A,C