What is plant maintenance in SAP S/4HANA assets management? (Choose four.)
What is plant maintenance in SAP S/4HANA assets management? (Choose four.)A . Ensure a secure work environmentB . Structure technical assets and make the required information availableC . Secondary Costing Element: COD . Record the tasks performed and costs incurredE . Plan maintenance tasks and assign resourcesView AnswerAnswer: ABDE
You can structure a functional location according to spatial criteria, technical criteria or functional criteria.
You can structure a functional location according to spatial criteria, technical criteria or functional criteria. Determine whether this statement is true or false.A . FalseB . TrueView AnswerAnswer: B
What are always used in PM if a number of identically constructed objects have to be maintained?
What are always used in PM if a number of identically constructed objects have to be maintained?A . Product BOMsB . Error MessageC . Material BOMsD . Binary MessageView AnswerAnswer: C
What can be installed and dismantled at functional locations?
What can be installed and dismantled at functional locations? You can also monitor the installation times for a piece of equipment from both the functional location view and the equipment view.A . Use a java.xml.ws.WebServiceRef annotationB . Piece of equipmentC . Use a java.xml.ws.WebServiceContext annotationD . Use a HandlerChainView AnswerAnswer:...
How is vCenter HA different from vSphere HA?
How is vCenter HA different from vSphere HA?A . vCenter HA requires only an active and passive node.B . vCenter HA requires an external Platform Services Controller.C . vCenter HA requires Fault Tolerance.D . vCenter HA requires an active, passive, and witness node.View AnswerAnswer: D Explanation: Reference: https://nolabnoparty.com/en/vmware-vcenter-high-availability-setup-pt-1/
What is not to create a BOM for each technical object, but to create just one BOM, and then assign this to the relevant technical objects?
What is not to create a BOM for each technical object, but to create just one BOM, and then assign this to the relevant technical objects? This avoids the use of redundant BOMs.A . RequestB . ViewC . SessionD . The aimView AnswerAnswer: D
Where can you assign a main work center?
Where can you assign a main work center?A . Object list of a maintenance orderB . Task list headerC . Maintenance plan headerD . Task list operationView AnswerAnswer: B
Which one of the building blocks in HR (Human Resources) to build up an organizational structure?
Which one of the building blocks in HR (Human Resources) to build up an organizational structure?A . Balance Sheet: Assets & LiabilitiesB . Revenue (not in CO)C . Organizational UnitD . Non Operating Expenses/Revenues: ExpensesView AnswerAnswer: C
What is processed using a purchase requisition and a PO with the item category: Standard?
What is processed using a purchase requisition and a PO with the item category: Standard?A . External AssignmentB . The web client SSL handshakeC . The web server SSL handshakeD . File bufferingView AnswerAnswer: A
Which app type must be added to the snippet to resolve the issue?
Refer to the exhibit. While troubleshooting an error on an application descriptor for a Docker app in Cisco IOx (package.yaml), the app type appears to be missing. Which app type must be added to the snippet to resolve the issue?A . paasB . docker-vmC . dockerD . docker-appView AnswerAnswer: C