Which the following statement regarding networks are correct?
Project Structures Which the following statement regarding networks are correct? Note: there are 3 correct answers for this question.A . If a network activity requires more capacity than available in a work center, the system automatically proposes an alternative work center. B. You can assign more than one activity element...
What are the prerequisites?
Project Structures You are using assembly processing. You need to determine the delivery date of a sales order item with an account assignment to the project. What are the prerequisites? Note: There are 3 correct answers to this questionA . A bill of material with sales views B. A material...
You have saved a network and activates with assigned material components. As soon as you release the network, you receive the error message "Business transaction cannot be carried out" What could be the reason for this error message?
You have saved a network and activates with assigned material components. As soon as you release the network, you receive the error message "Business transaction cannot be carried out" What could be the reason for this error message?A . Missing budget for material components B. Missing reservations for material components...
What do you recommend to set up the requirement date for the component?
Your customer's projects are subject to recurring changes of date. The assembly activity has an earliest start date of February 10 and lasts until February 20. The customer wants to assign a material component so that this will be in stock 5 days in advance. Note: Every day is a...
Which statements apply to the maintenance of the actual start and finish?
You are using WBS elements and activities are NOT assigned. Which statements apply to the maintenance of the actual start and finish? Note: There are 2 correct answers to this questionA . You can only maintain the actual finish if all lower-level WBS elements have an actual finish date and...
Which statements describe planned and actual revenue for WBS elements? Note: There are 2 correct answers to this question
Which statements describe planned and actual revenue for WBS elements? Note: There are 2 correct answers to this questionA . Planned revenue requires a sales order assigned to a WBS element B. Planned revenue can be transferred from a sales quotation C. Actual revenue is posted via a billing plan...
For which objects can billing plans be created? Note: There are 2 correct answers to this question
For which objects can billing plans be created? Note: There are 2 correct answers to this questionA . WBS elements B. Project definition C. Sales order items D. MilestonesView AnswerAnswer: A,C
How are earliest dates and latest dates of activities scheduled?
How are earliest dates and latest dates of activities scheduled?A . Earliest dates are scheduled by backward scheduling, and latest dates by copying the earliest dates B. Earliest dates are scheduled by forward scheduling, and latest dates by backward scheduling C. Earliest dates and latest dates are scheduled by forward...
How can you reduce the overload of the work center?
You use networks and internal activities in your project. You have activated capacity requirements and notice that one work center is overloaded. You have no authorization to change the work center. How can you reduce the overload of the work center? Note: There are 2 correct answers to this questionA...
Which of the following statements describes subnetworks?
You want to use subnetworks during the project. Which of the following statements describes subnetworks?A . Maintenance orders can be defined as sub-network B. The scheduling type of a subnetwork is always copied from the superior network C. A subnetwork cannot be defined for a superior subnetwork. D. Subnetworks must...