Which of the following statements describes subnetworks?
You want to use subnetworks during the project. Which of the following statements describes subnetworks?A . Maintenance orders can be defined as sub-network B. The scheduling type of a subnetwork is always copied from the superior network C. A subnetwork cannot be defined for a superior subnetwork. D. Subnetworks must...
What do you check?
You used reductions to reduce the scheduled duration of all internally-processed activities in your project. However, the duration did not changed after overall network scheduling. What do you check? Note: There are 2 correct answers to this questionA . If the maximum reduction level is less than 100 B. If...
The__________________that you specify when you create a project definition is unique for the entire project. Choose the correct answer.
The__________________that you specify when you create a project definition is unique for the entire project. Choose the correct answer.A . Plant B. Controlling area C. Company code D. Planning departmentView AnswerAnswer: B
What is crucial for the implementation of revenues planning and posting for WBS elements?
Revenues & Payment Your customer wants to plans and post revenues for WBS elements. What is crucial for the implementation of revenues planning and posting for WBS elements?A . At least one WBS element must be a billing element. B. The indicator "Project type" must be set to "Customer project"....
How can you update the degree of processing for an activity?
How can you update the degree of processing for an activity?A . By using results analysis B. By changing the activity C. By scheduling the activity D. By confirming the activityView AnswerAnswer: D
What controls whether the delivery date is defined by the earliest or latest scheduled dates?
An external component is assigned to a network activity. The delivery date for the purchase requisition depends on the dates of the network activity. What controls whether the delivery date is defined by the earliest or latest scheduled dates?A . The network profile B. The control key C. The table...
Which statements apply to the maintenance of the actual start and finish?
You are using WBS elements and activities are NOT assigned. Which statements apply to the maintenance of the actual start and finish? Note: There are 2 correct answers to this questionA . You can only maintain the actual finish if all lower-level WBS elements have an actual finish date and...
Where can you assign the use status profile for WBS elements? Note: There are 3correct answers to this question
Where can you assign the use status profile for WBS elements? Note: There are 3correct answers to this questionA . In the project profile B. In the project version C. In the project type D. In the project definition of a standard WBS E. In the operative WBS elementView AnswerAnswer:...
What are the prerequisites for delivering materials from the project? Note: There are 2 correct answers to this question
What are the prerequisites for delivering materials from the project? Note: There are 2 correct answers to this questionA . A delivery document type must be configured B. A sold to party is necessary C. A shipping point is necessary D. A sales order must be created in advanceView AnswerAnswer:...
What could be the reason?
You have created an internally-processed network activity, and assigned a work center and the work. After saving, you discover that no planned costs are displayed in the cost element report for the activity. What could be the reason? Note: There are 3 correct answers to this questionA . The formula...