What benefit do they have when using delivery from project (CNSO)?
Materials Your customer use a tight (estrecha) integration between sales order and WBS with network to deliver finished and semi-finish product. What benefit do they have when using delivery from project (CNSO)?A . With delivery from projects You can generate goods issues for project without creating delivery documents. B. With...
How can you record external service activities with service master data? Note: There are 2 correct answers to this question
How can you record external service activities with service master data? Note: There are 2 correct answers to this questionA . Confirm the network activity for external service B. Confirm the activities in the Cross-Application Time Sheet (CATS) C. Post a goods receipt in the goods movement application (MIGO) D....
What do you recommend for milestone definition?
You plan an activity that starts on February 1 and finishes on February 28. For this activity, you want to define a milestone for February 10 which should NOT be changed through scheduling. What do you recommend for milestone definition?A . Enter an offset of -18 days to the finish...
What are the prerequisites for requirements grouping of materials?
Your customer wants to use requirements grouping in SAP Project System. What are the prerequisites for requirements grouping of materials? Note: There are 2 correct answers to this questionA . The materials must allow sales order or project stock B. The exact lot size procedure must be used C. The...
For which objects can billing plans be created? Note: There are 2 correct answers to this question
For which objects can billing plans be created? Note: There are 2 correct answers to this questionA . WBS elements B. Project definition C. Sales order items D. MilestonesView AnswerAnswer: A,D
What do you recommend to set up the requirement date for the component?
Your customer's projects are subject to recurring changes of date. The assembly activity has an earliest start date of February 10 and lasts until February 20. The customer wants to assign a material component so that this will be in stock 5 days in advance. Note: Every day is a...
What must you assign to the WBS element?
Cost & Budget. A customer wants to allocate overhead rates to a WBS element. What must you assign to the WBS element?A . Settlement rules B. Costing Sheet C. Investment profile. D. Results analysis keyView AnswerAnswer: A
What is the requisites for implement scheduling of events?
Material Your customer uses Progress Tracking for network components and mantains dates of events manually. They need to implement scheduling of events. What is the requisites for implement scheduling of events?A . Priority of events must be set. B. Scheduling parameters for material scheduling must be set. C. Events must...
Which of the following data can be maintained in a standard network? Note: There are 3 correct answers to this question
Which of the following data can be maintained in a standard network? Note: There are 3 correct answers to this questionA . Document information records B. Internally processed activities C. Basic dates for activities D. Material components E. RelationshipsView AnswerAnswer: B,D,E
How can availability control be activated?
You are using budgeting and active availability control. How can availability control be activated? Note: There are 2 correct answers to this questionA . Automatic activation with budget assignment B. Automatic activation with assignment to an investment program C. Background activation (CJBV - Activate Availability Control) l D. Automatic activation...