For which objects can billing plans be created? Note: There are 2 correct answers to this question
For which objects can billing plans be created? Note: There are 2 correct answers to this questionA . WBS elementsB . Project definitionC . Sales order itemsD . MilestonesView AnswerAnswer: A,D
Which the following statement regarding networks are correct?
Project Structures Which the following statement regarding networks are correct? Note: there are 3 correct answers for this question.A . If a network activity requires more capacity than available in a work center, the system automatically proposes an alternative work center.B . You can assign more than one activity element...
Which statement is valid regarding networks?
Which statement is valid regarding networks?A . A network activity can be assigned to several WBS elementsB . Material components can be assigned to activity elementsC . Relationships can be used to connect activities of different networksD . A network can be activity-account-assigned and header-account-assignedView AnswerAnswer: A
What standard report type provides an overview of adjustments on the budget?
Budgeting is implemented for projects. The budget has been adjusted several times. What standard report type provides an overview of adjustments on the budget?A . Structure overview for budgetsB . Hierarchical report on budget updatesC . Cost element report on budget updatesD . Line item report for budgetsView AnswerAnswer: B
Which object is relevant in assembly processing to create an assembly order for the SD document?
Which object is relevant in assembly processing to create an assembly order for the SD document?A . Project profileB . Item categoryC . Requirement classD . Control keyView AnswerAnswer: A
What are the prerequisites for delivering materials from the project? Note: There are 2 correct answers to this question
What are the prerequisites for delivering materials from the project? Note: There are 2 correct answers to this questionA . A delivery document type must be configuredB . A sold to party is necessaryC . A shipping point is necessaryD . A sales order must be created in advanceView AnswerAnswer:...
Which statements apply to the maintenance of the actual start and finish?
You are using WBS elements and activities are NOT assigned. Which statements apply to the maintenance of the actual start and finish? Note: There are 2 correct answers to this questionA . You can only maintain the actual finish if all lower-level WBS elements have an actual finish date and...
Which organizational structures are required for network activities? Note: There are 3 correct answers to this question
Which organizational structures are required for network activities? Note: There are 3 correct answers to this questionA . Controlling areaB . PlantC . Sales organizationD . Company codeE . Operating concernView AnswerAnswer: A,B,D
Which of the following transactions can you use to post actual cost for external processing?
Resources Which of the following transactions can you use to post actual cost for external processing? Note: there are 2 correct answer for this question.A . Approval of a service entry sheetB . Posting a goods receiptC . Creating a service entry sheetD . Approval of a good receipt.E ....
How can you do that?
Dates You have a project with a network, material and milestone. You want to plan an activity to start two days after its predecessor. How can you do that? Note: there are 2 correct answers for this question.A . Use an offset of two days for the relationship of both...