Which of the following shows the correct order of the commitment zones for a Scheduling Agreement:

Which of the following shows the correct order of the commitment zones for a Scheduling Agreement:A . Firm Zone, Trade-Off Zone, Forecast/Planning ZoneB . Trade-Off Zone, Firm Zone, Forecast/Planning ZoneC . Firm Zone, Forecast/Planning Zone, Trade-Off ZoneD . Forecast/Planning Zone, Trade-Off Zone, Firm ZoneView AnswerAnswer: A

April 19, 2025 No Comments READ MORE +

Which cXML message is used to send forecast data from IBP to SAP Business Network with Planning Collaboration.?

Which cXML message is used to send forecast data from IBP to SAP Business Network with Planning Collaboration.?A . ProductActivityMessageB . OrderRequestC . StatusUpdateRequestD . ProductReplenishmentMessageView AnswerAnswer: A

April 18, 2025 No Comments READ MORE +

Which standard output type is relevant for a Scheduling Agreement with Release document? Note: There are 2 correct answers to this question.

Which standard output type is relevant for a Scheduling Agreement with Release document? Note: There are 2 correct answers to this question.A . NEUB . LPF2C . LPJ1D . LPH1View AnswerAnswer: C D

April 14, 2025 No Comments READ MORE +

Where does a Buyer create a Scheduling Agreement release?

Where does a Buyer create a Scheduling Agreement release?A . SAP Integrated Business Planning (IBP)B . SAP Business NetworkC . SAP ERP systemD . SAP Ariba BuyingView AnswerAnswer: C

April 11, 2025 No Comments READ MORE +

Supplier Review, Commit and Submit

Supplier Review, Commit and SubmitView AnswerAnswer: D

April 9, 2025 No Comments READ MORE +

Which of the following transaction rules can the buyer enable during scheduling agreement configuration? Note: There are 3 correct answers to this question.

Which of the following transaction rules can the buyer enable during scheduling agreement configuration? Note: There are 3 correct answers to this question.A . Allow suppliers to use both JIT type and Forecast type releases for shipping.B . Allow suppliers to send order confirmations for scheduling agreements and scheduling agreement...

April 7, 2025 No Comments READ MORE +

When does the buyer update the status of the Quality Notification to "Complete"?

When does the buyer update the status of the Quality Notification to "Complete"?A . When the Inspection Lot is acceptedB . When the Quality Notification is updated with a root causeC . When the Quality Notification is closedD . When the Advance Ship Notice is deliveredView AnswerAnswer: A

April 5, 2025 No Comments READ MORE +

Which are key features of Multi-Tier Collaboration? Note: There are 2 correct answers to this question.

Which are key features of Multi-Tier Collaboration? Note: There are 2 correct answers to this question.A . Multiple suppliers and logistics providers can be a part of the Multi-Tier order.B . Copy Suppliers can have visibility to Purchase Orders, Order Confirmations, and Advance Ship Notices.C . Suppliers can provide manufacturing...

April 3, 2025 No Comments READ MORE +

Which cXML message is used to send forecast data from IBP to SAP Business Network with Planning Collaboration.?

Which cXML message is used to send forecast data from IBP to SAP Business Network with Planning Collaboration.?A . ProductActivityMessageB . OrderRequestC . StatusUpdateRequestD . ProductReplenishmentMessageView AnswerAnswer: A

April 1, 2025 No Comments READ MORE +

Which documents can a Buyer create in the ERP from a Scheduling Agreement with Release? Note: There are 3 correct answers to this question.

Which documents can a Buyer create in the ERP from a Scheduling Agreement with Release? Note: There are 3 correct answers to this question.A . Scheduling Agreement Release (JIT)B . Ship noticeC . Goods receiptD . Scheduling Agreement Release (Forecast)E . Order confirmationView AnswerAnswer: A C D

March 29, 2025 No Comments READ MORE +