Which of the following are benefits of using ready-to-use content? There are 2 correct answers to this question

Which of the following are benefits of using ready-to-use content? There are 2 correct answers to this questionA . Minimized total cost of ownershipB . CD Predictable resultsC . Run SAP like a factoryD . Fast time-to-valueView AnswerAnswer: A, D

January 1, 2024 No Comments READ MORE +

In which phase will the customer develop a preliminary strategy for building A target operation and support organisational model?

In which phase will the customer develop a preliminary strategy for building A target operation and support organisational model?A . Discover phaseB . Prepare phaseC . Run phaseD . Explore phaseView AnswerAnswer: B

December 30, 2023 No Comments READ MORE +

What tool provides sizing estimators for the "system conversion" transition path?

What tool provides sizing estimators for the "system conversion" transition path?A . SAP readiness checkB . Scope and effort analyserC . SAP best practices explorerD . SAP Transformation navigatorView AnswerAnswer: A

December 30, 2023 No Comments READ MORE +

What are the responsibilities of the product owner in release and sprint planning? NOTE: There are 2 correct answers to this question.

What are the responsibilities of the product owner in release and sprint planning? NOTE: There are 2 correct answers to this question.A . Analyse the functional and technical dependencies between user storiesB . Prioritize backing user stories by business priorityC . Define objectives for each releaseD . Estimate the backing...

December 29, 2023 No Comments READ MORE +

Why is there NO sandbox system in the "New Implementation of SAP S/4HANA cloud Single Tenant?

Why is there NO sandbox system in the "New Implementation of SAP S/4HANA cloud Single Tenant?A . Because the project team uses the DEV system to confirm solution fitB . Because SAP S/4HANA cloud, single tenant edition, contains predefined businessC . Because the customer may use the SAP model companyD...

December 28, 2023 No Comments READ MORE +

Who determines the tasks that are required to complete the committed backlog items in a sprint?

Who determines the tasks that are required to complete the committed backlog items in a sprint?A . Scrum masterB . Product ownerC . Project managerD . Project teamView AnswerAnswer: D

December 28, 2023 No Comments READ MORE +

Which tool can you use to collaborate with other SAP activate methodology practitioners?

Which tool can you use to collaborate with other SAP activate methodology practitioners?A . SAP JamB . SAP solution managerC . SAP Roadmap viewerD . SAP implementation AssistantView AnswerAnswer: A

December 28, 2023 No Comments READ MORE +

What is the difference between the "new implementation of SAP S/4HANA Cloud" And the "new implementation of SAP S/4HANA transition path? There are 2 correct answers to this question.

What is the difference between the "new implementation of SAP S/4HANA Cloud" And the "new implementation of SAP S/4HANA transition path? There are 2 correct answers to this question.A . Different sets of workstreams are used for these transition pathsB . SAP S/4HANA uses the implementation guide (IMG) and the...

December 28, 2023 No Comments READ MORE +

What is SAP activate?

What is SAP activate?A . A methodology for each of the deployment modes (cloud, on premise, hybrid)B . A bundle of ASAP, SAP launch, and rapid deployment solutionsC . Step-by-step instructions on how to move from SAP best practices to your custom solutionsD . A solution adoption frameworkView AnswerAnswer: A

December 27, 2023 No Comments READ MORE +

What criterion does the product owner use to sequence the product backlog?

What criterion does the product owner use to sequence the product backlog?A . Relative effortB . Resource availabilityC . Business priorityD . ComplexityView AnswerAnswer: C

December 26, 2023 No Comments READ MORE +