Which accelerations can you use during the Scope Validation/Fit-Gap Analysis activity in the Explore Phase? There are 2 correct answers to this question.
Which accelerations can you use during the Scope Validation/Fit-Gap Analysis activity in the Explore Phase? There are 2 correct answers to this question.A . Sprint Backlog TemplateB . RICEF Specification TemplateC . Solution Validation WorkshopD . Quality Gate ChecklistView AnswerAnswer: B,C
What does a project jump-start include for a new implementation of SAP S/4HANA on-premise edition? Please choose the correct answer.
What does a project jump-start include for a new implementation of SAP S/4HANA on-premise edition? Please choose the correct answer.A . SAP Best PracticesB . Rapid prototypingC . Project team trainingD . Full project SCRUMView AnswerAnswer: A
What is the hierarchy level under Phase in the SAP Jam space for SAP Activate on-premise? Please choose the correct answer.
What is the hierarchy level under Phase in the SAP Jam space for SAP Activate on-premise? Please choose the correct answer.A . Key DeliverableB . ScenarioC . Work StreamD . TaskView AnswerAnswer: A
In which phase of the SAP Activate Methodology does the team complete the System Assessment? Please choose the correct answer.
In which phase of the SAP Activate Methodology does the team complete the System Assessment? Please choose the correct answer.A . DeployB . ExploreC . PrepareD . RealizeView AnswerAnswer: C
What is the purpose of the SAP Activate Methodology? Please choose the correct answer.
What is the purpose of the SAP Activate Methodology? Please choose the correct answer.A . To enable access to the SAP ecosystemB . To accelerate the initial implementation of SAP S/4HANAC . To provide end-to-end integrated application lifecycle managementD . To manage project and solution documentationView AnswerAnswer: B
What is the most granular level of the methodology you can view in the Roadmap Viewer? Please choose the correct answer.
What is the most granular level of the methodology you can view in the Roadmap Viewer? Please choose the correct answer.A . ScenarioB . TaskC . DeliverablesD . PhaseView AnswerAnswer: B
Which navigation option do you use in the Roadmap Viewer to access the SAP Activate Methodology content? Please choose the correct answer.
Which navigation option do you use in the Roadmap Viewer to access the SAP Activate Methodology content? Please choose the correct answer.A . Navigate by assigned Delivery ModeB . Navigate by RACI matrix accountabilityC . Navigate by work streamD . Navigate by Project Team Member RoleView AnswerAnswer: C
In which phase you execute the User Acceptance Test? Please choose the correct answer.
In which phase you execute the User Acceptance Test? Please choose the correct answer.A . Build and TestB . DeployC . Final PreparationD . RealizeView AnswerAnswer: D
What are key characteristics of the implementation approach in SAP Activate Methodology? There are 3 correct answers to this question.
What are key characteristics of the implementation approach in SAP Activate Methodology? There are 3 correct answers to this question.A . Premium engagement readyB . On-premise onlyC . Fixed scopeD . Validate solutionE . Start with SAP Best PracticesView AnswerAnswer: A,D,E
What do you do during post cutover? Please choose the correct answer.
What do you do during post cutover? Please choose the correct answer.A . Setup Operational SupportB . Perform the Verification Session of the SAP Going Live CheckC . Perform Technical System TestD . Conduct Organizational Readiness CheckView AnswerAnswer: B