Which of the following is part of the Explore phase in the "New implementation od SAP S/4 HANA Cloud" transition path?
- A . Simplification and custom code impact analysis
- B . Setup and enablement
- C . Fit-to-standard
- D . Solution validation and Delta design
How can a customer get access to SAP Cloud ALM?
- A . SAP Cloud ALM fair usage rights are included in SAP Enterprise Support, cloud editions at NO additional cost
- B . SAP Cloud ALM fair usage rights are included in SAP Preferred Success and SAP Preferred Care at NO additional cost
- C . SAP Cloud ALM fair usage rights are included in SAP May Attention and SAP Active Attention at NO additional cost
- D . SAP Cloud ALM can be bought on the SAP Store
What tool provides guidance on replacing custom code developed for SAP ERP with SAP S/4HANA functionality for the system conversion?
- A . Simplification item check (Si-check)
- B . Software provisioning manager
- C . SAP code inspector
- D . Software update manager with database migration option
Which activity helps the project team to add the user stories to the product backlog? Please choose the answer.
- A . Planning the User Acceptance Test
- B . Conducting the Solution Validation
- C . Assessing Project Risks
- D . Preparing a Project Schedule
In which SAP Activate methodology phase does the team identify and design functional quick wins in scope of the conversion project? Please choose the answer.
- A . Realize
- B . Deploy
- C . Prepare
- D . Explore
What is the correct order of the SAP Activate Methodology phases?
- A . Prepare -> Discover -> Explore -> Realize -> Deploy -> Run
- B . Discover -> Prepare -> Explore -> Realize -> Deploy -> Run
- C . Plan -> Build -> Run -> Sustain
- D . Plan -> Design -> Build -> Operate
The activities in the transition path of SAP S/4HANA Cloud, Single-Tenant Edition (STE) and SAP S/4HANA Cloud are very similar, what are the major differences?
- A . SAP S/4HANA Cloud STE is configured through IMG while SAP S/4HANA Cloud through SSCUI’s.
- B . Different tools are used to manage Application Lifecycle of SAP S/4HANA Cloud STE.
- C . SAP S/4HANA Cloud STE has shorter release cycles comparing to SAP S/4HANA Cloud.
- D . SAP S/4HANA Cloud STE has longer release cycles comparing to SAP S/4HANA Cloud.
Who determines the priority of user stories in the backlog of an Agile project?
- A . Project Team
- B . SCRUM Master
- C . Project Manager
- D . Product Owner
What is SAP Activate? Please choose the answer.
- A . A combination of SAP best practices, methodology, and guided configuration
- B . A methodology for each of the deployment modes (cloud, on-premise, hybrid)
- C . A step-by-step instruction on how to remove from SAP best practices to your custom solution
- D . A bundle of ASAP, SAP Launch, and Rapid Deployment Solutions
Which activities are critical for delivering Agile projects? There are 2 answers to this question.
- A . Blueprint scheduling
- B . Release planning
- C . Sprint planning
- D . Retrospective agenda creation