You are configuring internal order settlement .
What do you define which cost element should be settled, using either the original settlement cost elements?
- A . Credit component (of the costing sheet)
- B . Allocation structure
- C . Settlement profile
- D . Settlement rule
You have implemented Product Cost by Sales Oder in conjunction with revenue-based results analysis in your organization.
For a particular sales order item, you have the following:
Plan revenue = 3000; Plan costs = 2000
Actual revenue = 1200; Actual costs = 1000
What data does the system calculate during results analysis?
- A . Revenue = 1200; Cost of sales = 800; Reserve = 200
- B . Revenue = 1200; Cost of sales = 1000; Reserve = 200
- C . Revenue = 1200; Cost of sales = 1000; WIP = 200
- D . Revenue = 1200; Cost of sales = 800; WIP = 200
Which statements best describes a single cost center standard hierarchy?
- A . It is a structure to which all cost center groups create for a controlling area are assigned.
- B . It is a structure to which all cost center groups created within an operating concern are assigned.
- C . It is a structure to which all the cost centers within an operating concern are assigned.
- D . It is a structure to which all the cost centers within a controlling area are assigned.
In the material master record there are three planned prices: ""Planned price 1"", ""Planned price 2""and""Planned price 3"" .
What do you use them for?
- A . To valuate goods movement
- B . To valuate the materials in cost estimates
- C . To valuate material stocks
- D . To update the standard price during the release of a standard cost estimate
Which type of Profitability Analysis updates the cost of goods sold at the time of delivery?
- A . Periodic-accounting based
- B . Both account-based and costing-based
- C . Account-based only
- D . Costing-based only
You create a new profit center .
Which company code(s) is it assigned to by default?
- A . All company codes where profit center accounting is activated.
- B . All company codes maintained in your authorization profile.
- C . All company codes within the controlling area.
- D . All company codes to which the profit center standard hierarchy is assigned to.
Which of the following statements best describe Product Cost by Period? Note: There are 2 correct answers to this question.
- A . It is used when periodic costs outweigh daily postings.
- B . It is used to analyze work in process (WIP) based on actual costs.
- C . It is used when the focus of controlling is on a stable and continuous production process.
- D . It is used in conjunction with a product cost collector.
You are considering using commitment management with internal orders .
What do you need to do in the configuration?
- A . Activate commitment management in both the controlling area and the order type.
- B . Activate commitment management in the controlling area, the order type, and in individual internal order master data.
- C . Activate commitment management in both the version and the order type.
- D . Activate commitment management only in the controlling area.
For which objects can you enter statistical key figures? Note: There are 3 correct answers to this question.
- A . Cost centers
- B . Internal orders
- C . Functional areas
- D . Cost elements
- E . Profit centers
You want to determine which operations of the routing should be considered in a product cost calculation .
How do you do this? Note: There are 2 correct answers to this question.
- A . By marking the cost indicator in the control key assigned to the operation
- B . By marking the Relevance to Costing indicator in the operation
- C . By assigning a cost center to the work center in the operation
- D . By defining a usage key in the header of the routing.
You want to maintain a cost component structure .
What can you determine for each cost component? Note: There are 3 correct answers to this question.
- A . Relevance of cost component to inventory valuation
- B . Assignment of cost component to calculation base for overheads in costing sheet
- C . Relevance of cost component to results analysis
- D . Relevance of cost component to goods manufactured
- E . Assignment of cost component of cost component group
What are some of the characteristics of SAP Core Data Services (CDS) views? Note: There are 3 correct answers to this question.
- A . CDS views are considered system modifications.
- B . CDS views have ready-to-use content.
- C . CDS views duplicate data for reporting efficiencies.
- D . CDS views have no latency.
- E . CDS views support authorization.
In which module do you process profit center allocations in SAP S/4HANA?
- A . Product cost accounting
- B . General ledger accounting
- C . Account-based profitability analysis
- D . Cost center accounting
What are some of the objectives of Profitability Analysis? Note: There are 2 correct answers to this question.
- A . Provide the company with information on the performance of its market segments.
- B . Allow the company to determine if the sales force achieved their contribution margin goals.
- C . Provide the company with a detailed view of its financial statements by areas of responsibilities.
- D . Allow the company to determine standard costs and revenues according to the period accounting method.
In a standard system delivery, how many free characteristics can be added to an operating concern?
- A . 0-70
- B . 101-150
- C . 71-100
- D . Over 150
What can you do with statistical internal orders?
- A . Apply overhead rates to the internal order.
- B . Settle costs to a cost center.
- C . Simultaneously post to a cost center.
- D . Transfer posting to another internal order.
Which scenarios can be covered by one single costing run? Note: There are 2 correct answers to this question.
- A . Inventory cost estimate of all the materials in one plant
- B . Standard cost estimate of all the materials in all plants of a controlling area
- C . Current cost estimate of all the materials in all controlling area
- D . Product cost collector cost estimate in one plant
What parameters can you set up when defining order types?
- A . Define document type.
- B . Define default parameters for master record fields.
- C . Define source structure.
- D . Allow revenue postings.
Which of the following objects can be selected in templates for activity-based costing? Note: There are 2 correct answers to this question.
- A . Cost center/activity type
- B . Internal order
- C . WBS element
- D . Business process
How does the system derive the requirement type from the material master data? Note: There are 2 correct answers to this question.
- A . MRP group -> requirements class -> planning strategy -> requirements type
- B . MRP group -> Strategy group -> planning strategy -> requirements type
- C . Strategy group -> planning strategy -> requirements class -> requirements type
- D . Strategy group -> planning strategy -> requirements type
Which statement best describes the Query Browser for reporting?
- A . It is a desktop browser that integrates with SAP S/4HANA.
- B . It is the frontend used to define reports in Analysis for Office.
- C . It is available as an additional license product in SAP S/4HANA.
- D . It is a design studio app that comes as standard SAP Fiori content.
Which parameters are controlled by the costing type in a costing variant? Note: There are 2 correct answers to this question.
- A . Save with date key
- B . Price updates
- C . Costing sheet
- D . Price for materials
You are implementing SAP S/4HANA and you want to run analytical reports off a single data model .
Which statement best describes reporting in SAP S/4HANA?
- A . Reporting can be either broad and deep for analysis, or speedy and simple, but not both.
- B . Reporting on data in real time is difficult, and complex to design.
- C . Reporting on data is available in real-time at every level of detail.
- D . Reporting analytical data is always done in a business warehouse system.
Which of the following statements apply to SAP S/4HANA embedded analytics? Note: There are 2 correct answers to this question.
- A . It is hosted on the SAP Cloud Platform and integrate seamlessly on the SAP S4/HANA on the Fiori Launchpad.
- B . It is the core SAP S4/HANA license and users the same technical stack and user interface.
- C . It uses core data services (CDS) views to create virtual data models (VDMs ) for reporting.
- D . It is used by dedicated BI users who need to go beyond the capabilities of Strategic Analysis Tools for reporting.
To which object can you settle an internal order using cost elements with cost element category 21 (internal settlement)? Note: There are 3 correct answers to this question.
- A . Sales order item
- B . WBS element
- C . General ledger account
- D . Network
- E . Asset
At which level do you define the valuation method for results analysis?
- A . Controlling area
- B . Company code
- C . Plant
- D . Operating concern
You create alternative CO versions for your controlling area, in addition to version 0 .
What would you use additional CO versions for? Note: There are 2 correct answers to this question.
- A . To store data of alternative plan costing runs
- B . To store different plan data
- C . To store data of parallel valuation
- D . To store different budget data
You want to setup integrated planning for your internal order .
What do you need to do? Note: There are 2 correct answers to this question.
- A . Set the relevant indicators in the CO version.
- B . Set the relevant indicator in the controlling area.
- C . Set the relevant indicator in the planning profile of the order type.
- D . Set the relevant indicator in the internal order master record.
You want to understand why cost are collected on sales order item level .
What do you need to in the configuration? Note: There are 3 correct answers to this question.
- A . Requirement type
- B . Requirements class
- C . Valuation variant
- D . Costing type
- E . Account assignment category
What are some of the characteristics of planning for internal orders? Note: There are 2 correct answers to this question.
- A . You can plan multiple versions.
- B . You can enter costs and revenues.
- C . You can define tolerance limits for plan overspend.
- D . Availability control can check against plan values.