Your production planners must execute planning only for specific resources.
How can you achieve this in Advanced Planning (PP/DS)?
- A . Use a propagation range.
- B . Use a resource group
- C . Use a planning area.
- D . Use a planning group.
in your Plant, MRP is activated.
which options do you have to exclude a material from the MRP run? Note: there are 2 correct answers to this question.
- A . Use a specific material status
- B . Use a specific material group
- C . Use a specific MRP type
- D . Use a specific MRP list
How can you support a GMP (Good Manufacturing Practice)-compliant production process? Note: There are 3 correct answers to this question.
- A . Approved resources
- B . Digital signature
- C . Batch record
- D . GMP-compliant flag
- E . Recipe approval
How can you support a GMP (Good Manufacturing Practice)-compliant production process? Note: There are 3 correct answers to this question.
- A . Approved resources
- B . Digital signature
- C . Batch record
- D . GMP-compliant flag
- E . Recipe approval
Your project uses process orders for the production of liquid chemicals.
What can you define to ensure that production flow only happens in suitable and physically connected tanks? Note: There are 2 correct answers to this question.
- A . Resource matrix
- B . Resource network
- C . Resource hierarchy
- D . Resource selection
How can you limit the validity of a bill of material (BOM)? Note: There are 2 correct answers to this question,
- A . By Plant
- B . By Period
- C . By Industry
- D . By Material Status
Why would you use phantom assemblies? Note: There are 3 correct answers to this question.
- A . To increase the number of planning levels
- B . To simplify the structure of bills of material
- C . To reduce the number of material masters
- D . To make the assignment of components easier
- E . To reduce the number of changes required in bills of material
Which of the following questions do you have to answer before you start creating a bill of material (BOM)?
- A . Is the material type allowed in the BOM?
- B . Which base unit of measure does the material have?
- C . What status does the BOM have?
- D . In which storage location is the BOM required?
Advanced Planning uses master data and transaction data from SAP S/4HANA.
In which data objects can you set the Advanced Planning flag? Note: There are 2 correct answers to this question.
- A . Work Center
- B . Production Version
- C . Material
- D . plant
What time element of midpoint scheduled operations can be reduced by reduction strategy settings while dispatching? Note: There are 2 correct answers to this question
- A . Queue
- B . Teardown time
- C . Move time
- D . Setup Time