Which of the following are possible configuration steps when setting up the alert monitor in Advanced Planning? Note: There are 2 correct answers to this question.
- A . Create an object selection variant for priority-category-related alerts.
- B . Assign the alert profile to the overall profile.
- C . Create an object selection variant for production-planning-related alerts.
- D . Assign the overall profile to the authorization profile.
where does the system check master data selection settings during the creation of planned orders and production orders? Note: There are 3 Correct answers to this question.
- A . in the bill of material (BOM)
- B . in the work centers
- C . in the MRP controller
- D . In the routing
- E . in the production version
You use planning strategy Finite Scheduling with Reverse and want to allow scheduling the past.
How can you parameterize this in the strategy profile?
- A . Specify a negative planning horizon.
- B . Specify a positive planning horizon.
- C . Specify a positive offset time.
- D . Specify a negative offset time.
What is the purpose of a reporting point confirmation in repetitive manufacturing? Note: There are 2 Correct answers to this question?
- A . To determine the work in progress along the production line
- B . To provide timely updates of inventory management for the staged components
- C . To reduce the total production lead time for a long production line
- D . To stage different components for a production line simultaneously
Generic Parent » Generic 1 pt
What is the purpose of collective orders?
- A . To manage production orders for an entire finished product on multiple levels
- B . To combine order management of co-products and by-products with the main product
- C . To post production costs on a cost collector instead of the production order
- D . To post any component withdrawal as single backflush with order confirmation
You want to schedule an operation finitely, without removing other operations.
Which scheduling strategy do you select?
- A . Insert operation
- B . Squeeze in
- C . Schedule in working time only
- D . Find Slot
When you create a sales order
When can consumption of planned independent requirements take place for planning strategy 40 (Planning with final assembly?
- A . When MRP creates a dependent requirement
- B . When MRP creates a planned order
- C . When you create a sales order
- D . When MRP creates a planned order
What are the consequences when you assign a planned order to a production line manually, using the planning table in repetitive manufacturing?
- A . The planned order is converted to a production order.
- B . The planned order’s component availability is checked.
- C . The planned order generates capacity requirements
- D . The planned order’s components are copied to the picking list.
During production order creation, several valid production versions are found.
How does the system choose the production version?
- A . Lot size or material cost
- B . Validity period or sales order
- C . Planned order or material number
- D . Alphanumeric or quota arrangement
What data can you maintain in the subitems of a bill of material (BOM)? Note: There are 2 correct answers to this question.
- A . Installation point
- B . Item type
- C . Quantity
- D . Scrap percentage