Question #1

Where do you maintain the duration of a production operation?

  • A . Bill of material (BOM)
  • B . Work instructions
  • C . Material master
  • D . Routing

Reveal Solution Hide Solution

Correct Answer: D
Question #2

You want to triggering-house production of a semi-finished mater al before a sales order for the corresponding finished good is received .

Which planning strategy supports the consumption of planned independent requirements for the semi-finished material?

  • A . Make-to-order production (20)
  • B . Planning without final assembly (50)
  • C . Planning with final assembly (40)
  • D . Planning at assembly level (70)

Reveal Solution Hide Solution

Correct Answer: B
Question #3

In a production process, you need acertain amount of liquid as input material. The source tank is directly connected to the reactor .

How can you process consumption postings?

  • A . Kanban
  • B . Picking list
  • C . Backflushing
  • D . Transfer Order

Reveal Solution Hide Solution

Correct Answer: B
Question #4

For a production version to be valid and consistent what requirements must be fulfilled?

Note: There are 3 correct answers to this question.

  • A . The lot size range must be within the lot-size range of the assigned routing.
  • B . The assigned routing must be a rate routing.
  • C . The deletion flag must NOT be set for the bill of materials (BOM) or the routing.
  • D . The assigned routing and bill of materials (BOM) must be valid in the entire validity period.
  • E . The assigned routing must NOT have alternative sequences.

Reveal Solution Hide Solution

Correct Answer: A,C,D
Question #5

Which bill of material (BOM) categories can you define in SAP S/4HANA? Note: There are 2 correct answers to this question.

  • A . Functional Location BOM
  • B . Sales Order BOM
  • C . Class BOM
  • D . Work Center BOM

Reveal Solution Hide Solution

Correct Answer: A,B
Question #6

What does forecasting in the demand planning cycle include? Note: There are 3 correct answers to this question.

  • A . Market intelligence
  • B . Past quotation quantities
  • C . Past procurement quantities
  • D . One-off events
  • E . Past sales order quantities

Reveal Solution Hide Solution

Correct Answer: A,D,E
Question #7

In your project,you have several materials that are planned by different people .

How can

you assign the planning responsibility?

  • A . MRP type
  • B . MRP group
  • C . MRP controller
  • D . MRP planning file

Reveal Solution Hide Solution

Correct Answer: C
Question #8

What are the possible results of a production planning run in Advanced Planning (PP/OS)? Note: There are 3 correct answers to this question.

  • A . Stock transport order
  • B . Production order
  • C . Scheduling agreement schedule line
  • D . Purchase requisition
  • E . Planned order

Reveal Solution Hide Solution

Correct Answer: C,D,E
Question #9

You want to reduce planning efforts for B/C materials .

Which planning procedure do you recommend?

  • A . Manual planning without check
  • B . Forecast planning
  • C . Material requirements planning
  • D . Consumption-based planning

Reveal Solution Hide Solution

Correct Answer: D
Question #10

How can SAP S/4HANA support a GMP compliant production process? Note: There are 3 correct answers to this question.

  • A . Documentation of quality data with Quality Management
  • B . Predefined GMP compliant process order types to meet audit requirements
  • C . Use of the GMP compliant flag in relevant master data applications
  • D . Use of the digital signature function to check and run business processes
  • E . Recipe approval (with Engineering Change Management)

Reveal Solution Hide Solution

Correct Answer: A,D,E

Question #11

What are possible configuration steps when setting up the alert monitor in Advanced Planning? Note: There are 3 correct answers to this question.

  • A . Create object selection variant for transportation lane-related alerts.
  • B . Assign the alert profile to the overall profile.
  • C . Create object selection variant for product-related alerts.
  • D . Assign the overall profile to the authorization profile.
  • E . Create object selection variant for resource-related alerts

Reveal Solution Hide Solution

Correct Answer: B,C,E
Question #12

Which of the following elements does MRP take into account during net requirement calculation? Note: There are 2 correct answers to this question.

  • A . Maximum stock level
  • B . Purchase orders
  • C . Safety stock
  • D . Lot size

Reveal Solution Hide Solution

Correct Answer: C,D
Question #13

In which data objects do you maintain the production line as the work center for repetitive manufacturing? Note: There are 2 correct answers to this question.

  • A . Production version
  • B . Production cost collector
  • C . Routing
  • D . Repetitive manufacturing profile

Reveal Solution Hide Solution

Correct Answer: A,C
Question #14

What is a work center hierarchy in SAP S/4HANA capacity planning?

  • A . A group of alternative work centers for production, structured in hierarchy levels by prior ties
  • B . A group of work centers in a parallel sequence that is used to split product on quantities and work on them in parallel
  • C . A group of work centers in a production line being used in sequence for production
  • D . A group of alternative work centers providing a cumulative available capacity for production

Reveal Solution Hide Solution

Correct Answer: D
Question #15

Your project team decides to use a make-to-order planning strategy for a strategic material in discrete manufacturing .

What is the impact of this decision? Note: There are 3 correct answers to this question.

  • A . Sales order-specific planning run is required.
  • B . Sales order-specific stock is created
  • C . Net requirements calculation is sales order-specific.
  • D . Storage location MRP areas are required.
  • E . Production orders are created with sales order reference.

Reveal Solution Hide Solution

Correct Answer: B,C,E
Question #16

Which actions does the system perform by default when you save a confirmation for a finished product in repetitive manufacturing? Note: There are 3 correct answers to this question.

  • A . Archiving of documents for assembly scrap
  • B . Posting of production costs to the production cost collector
  • C . Reduction of associated capacity requirements
  • D . Material staging for next order in sequence
  • E . Posting of goods receipt for the product

Reveal Solution Hide Solution

Correct Answer: B,C,E
Question #17

In your plant, MRP is activated .

Which options do you have to exclude a material from the MRP run? Note: There are 2 correct answers to this question.

  • A . Use a specific material status.
  • B . Use a specific MRP controller.
  • C . Use a specific material group
  • D . Use a specific MRP type.

Reveal Solution Hide Solution

Correct Answer: B,D
Question #18

Mode selection is one of the scheduling options available in Advanced Planning in SAP S/4HANA. When can you use mode selection?

  • A . When multiple planned orders exists in one resource
  • B . When alternate resourcesare used within one operation
  • C . When multiple production versions are maintained for one product
  • D . When multiple operations are maintained for one product

Reveal Solution Hide Solution

Correct Answer: B
Question #19

Why would you use phantom assemblies? Note: There are 3 correct answers to this question.

  • A . To make the assignment of components easier
  • B . To simplify the structure of bills of material
  • C . To reduce the number of changes required in bills of material
  • D . To increase the number of planning levels
  • E . To reduce the number of material masters

Reveal Solution Hide Solution

Correct Answer: A,B,C
Question #20

Your quality department detects a deviation in a raw material batch. Unfortunately, this batch has already been used in production .

How can you identify all affected finished goods stocks?

  • A . Use the material staging report.
  • B . Use the batch information cockpit.
  • C . Use the material where-used report.
  • D . Use batch determination.

Reveal Solution Hide Solution

Correct Answer: B

Question #21

Which materials have a negative quantity in a bill of materials or in a recipe? Note: There are 3 correct answers to this question.

  • A . By-products
  • B . Bulk materials
  • C . Waste products
  • D . Continuous flow materials
  • E . Co-products

Reveal Solution Hide Solution

Correct Answer: A,C,E
Question #22

You have maintained the parameters for simple discontinuation the material master of a component .

Which business process will be affected if the available stock is zero and the discontinuation date is in the past?

  • A . Back flushing
  • B . Material requirements planning
  • C . Production order release
  • D . Kanban

Reveal Solution Hide Solution

Correct Answer: B
Question #23

You want to set up a make-to-order planning scenario for a finished material. Some components from the bill of materials (BOM) should be procured per sales order, other components should be procured for various requirements. Fore casting is NOT possible .

Which settings do you make to achieve this?

  • A . Planning strategy 50 (Planning without final assembly) and the corresponding Mixed MRP indicator
  • B . Planning strategy 20 (Make-to-Order) and the corresponding individual Collective indicator
  • C . Planning strategy 20 (Make-to-Order) and the corresponding Mixed MRP indicator
  • D . Planning strategy 50 (Planning without final assembly) and the corresponding individual Collective Indicator.

Reveal Solution Hide Solution

Correct Answer: D
Question #24

Advanced Planning uses master data and transaction data from SAP S/4HANA In which data obje can you set the advanced planning flag? Note: There are 2 correct answers to this question.

  • A . Work center
  • B . Material
  • C . Production version
  • D . Plant

Reveal Solution Hide Solution

Correct Answer: A,B
Question #25

You want to create a production order from a planned order .

What methods could you use?

Note: There are 2 correct answers to this question.

  • A . Full conversion
  • B . Order release
  • C . Individual conversion
  • D . Partial conversion

Reveal Solution Hide Solution

Correct Answer: A,D
Question #26

Duringproduction order creation, several valid production versions are found .

How does the system choose the product conversion?

  • A . Validity period or sales order
  • B . Lot size or material cost
  • C . Alphanumeric or quota arrangement
  • D . Planned order or materialnumber

Reveal Solution Hide Solution

Correct Answer: C
Question #27

What is the purpose of a reporting point confirmation in repetitive manufacturing? Note:

There are 2 correct answers to this question.

  • A . To determine the work in progress along the production line
  • B . To provide timely updates of inventory management for the staged components
  • C . To stage different components for a production line simultaneously
  • D . To reduce the total production lead time for along production line

Reveal Solution Hide Solution

Correct Answer: A,B
Question #28

You want to schedule an operation finitely, without moving other operations .

Which scheduling strategy do you select?

  • A . Scheduling working time only
  • B . Find Slot
  • C . Insert operation
  • D . Squeezing

Reveal Solution Hide Solution

Correct Answer: B
Question #29

When working with both cross-plant and plant-specific material statuses in the mater al master, which status has the highest priority?

  • A . The least restrictive status
  • B . The cross-plant status
  • C . The plant-specific status
  • D . The most restrictive status

Reveal Solution Hide Solution

Correct Answer: D
Question #30

In the Schedule Production app, which settings can you make in the planning strategy? Note: There are 3 correct answers to this question.

  • A . Fixed pegging (on/off)
  • B . Planning mode (bucket/sequence)
  • C . Finiteness level (0…1)
  • D . Direction (forward/backward)
  • E . Scheduling control (finite/infinite)

Reveal Solution Hide Solution

Correct Answer: B,D,E