Where do you maintain the duration of a production operation?
- A . Bill of material (BOM)
- B . Work instructions
- C . Material master
- D . Routing
You want to triggering-house production of a semi-finished mater al before a sales order for the corresponding finished good is received .
Which planning strategy supports the consumption of planned independent requirements for the semi-finished material?
- A . Make-to-order production (20)
- B . Planning without final assembly (50)
- C . Planning with final assembly (40)
- D . Planning at assembly level (70)
In a production process, you need acertain amount of liquid as input material. The source tank is directly connected to the reactor .
How can you process consumption postings?
- A . Kanban
- B . Picking list
- C . Backflushing
- D . Transfer Order
For a production version to be valid and consistent what requirements must be fulfilled?
Note: There are 3 correct answers to this question.
- A . The lot size range must be within the lot-size range of the assigned routing.
- B . The assigned routing must be a rate routing.
- C . The deletion flag must NOT be set for the bill of materials (BOM) or the routing.
- D . The assigned routing and bill of materials (BOM) must be valid in the entire validity period.
- E . The assigned routing must NOT have alternative sequences.
Which bill of material (BOM) categories can you define in SAP S/4HANA? Note: There are 2 correct answers to this question.
- A . Functional Location BOM
- B . Sales Order BOM
- C . Class BOM
- D . Work Center BOM
What does forecasting in the demand planning cycle include? Note: There are 3 correct answers to this question.
- A . Market intelligence
- B . Past quotation quantities
- C . Past procurement quantities
- D . One-off events
- E . Past sales order quantities
In your project,you have several materials that are planned by different people .
How can
you assign the planning responsibility?
- A . MRP type
- B . MRP group
- C . MRP controller
- D . MRP planning file
What are the possible results of a production planning run in Advanced Planning (PP/OS)? Note: There are 3 correct answers to this question.
- A . Stock transport order
- B . Production order
- C . Scheduling agreement schedule line
- D . Purchase requisition
- E . Planned order
You want to reduce planning efforts for B/C materials .
Which planning procedure do you recommend?
- A . Manual planning without check
- B . Forecast planning
- C . Material requirements planning
- D . Consumption-based planning
How can SAP S/4HANA support a GMP compliant production process? Note: There are 3 correct answers to this question.
- A . Documentation of quality data with Quality Management
- B . Predefined GMP compliant process order types to meet audit requirements
- C . Use of the GMP compliant flag in relevant master data applications
- D . Use of the digital signature function to check and run business processes
- E . Recipe approval (with Engineering Change Management)