Exam4Training

SAP C_TS413_1909 SAP Certified Application Associate – SAP S/4HANA Asset Management Online Training

Question #1

At what level does the system calculate costs of maintenance orders? choose 1 answer

  • A . always on header level depending on the maintenance plant
  • B . always on operation level depending on the order type and the maintenance planning plant
  • C . on header level or on operation level depending on the order type and the maintenance planning plant
  • D . on header level or on operation level depending on the controlling view

Reveal Solution Hide Solution

Correct Answer: C
Question #2

Which periode does the planner define when using the scheduling period in the maintenance plan? choose 1 answer

  • A . the period in which the system job for scheduling runs
  • B . the period for which orders are created in advance
  • C . the period in which a shift of planned dates is allowed
  • D . the period for which the system generate planned or call dates

Reveal Solution Hide Solution

Correct Answer: D
Question #3

Name the manufacturing execution process step that allows someone to enter the actual time and activities of the various operations during the production process.

  • A . Costing
  • B . Disaggregation
  • C . Material requirements planning
  • D . Confirmation

Reveal Solution Hide Solution

Correct Answer: D
Question #4

Inspections and repair work requiring the shutdown of an entire asset is performed atregular intervals can be handled using__________________.

  • A . Project-Oriented Maintenance
  • B . Preventive Maintenance
  • C . Corrective Maintenance
  • D . ABreakdown Maintenance

Reveal Solution Hide Solution

Correct Answer: A
Question #5

When the planner adds a stock material in the orders, which activities are performed next in relation to the order? choose 3 answers

  • A . perform the availablity check
  • B . post the goods receipt
  • C . post the goods issue
  • D . create the purchase order
  • E . print the material provision

Reveal Solution Hide Solution

Correct Answer: A,C,E
Question #6

What are the prerequisits to run SAP Work manager? choose 3 answers

  • A . Mobile add-on for SAP S/4 HANA
  • B . Sysbase unwired platform
  • C . SAP mobile platform
  • D . SAP Geographical enablement framework
  • E . device operation system ( ios, andriod or windows )

Reveal Solution Hide Solution

Correct Answer: A,C,E
Question #7

You plan to use the integration of maintenance order and project system (PS) objects. to which PS objects can you assign a maintenance order? choose 2 answers

  • A . network operation
  • B . WBS element
  • C . network header
  • D . project definition

Reveal Solution Hide Solution

Correct Answer: B,D
Question #8

SAP S/4HANA is built to natively integrate with business networks such as:

  • A . SAP Fieldglass
  • B . SAP Concur
  • C . Linkedin
  • D . SAP Hybris
  • E . SAP Ariba

Reveal Solution Hide Solution

Correct Answer: A,B,D,E
Question #9

How do you activate subscreen for equipement master data in customizing? choose 1 answer

  • A . create a view profile and assign it to the equipement category
  • B . create a screen group info type and assign the group to the equipment category
  • C . assign object information parameter to the equipement category
  • D . define the field selection for the equipment master data

Reveal Solution Hide Solution

Correct Answer: A
Question #10

The planner must add an activity to a notification which must be executed in the future .

Which option in the notification, that can be predefined in a catalog does the planner use? choose 1 answer

  • A . an activity in the notification item
  • B . a task in the notification header
  • C . a text in the notification item
  • D . a text in the subject long text screen

Reveal Solution Hide Solution

Correct Answer: B

Question #11

what is primary goal of sap perdictive maintenence and service? choose 1 answer

  • A . to precalculate maintenance projects
  • B . to provide advanced cost controlling analysis
  • C . to create a cloud-based equipement directory
  • D . to collect and analyze machine data

Reveal Solution Hide Solution

Correct Answer: A
Question #12

You would like to preset a value for a field that you have to enter frequently. To do this, you need the parameter ID .

Which help function would you use to locate the parameter ID when you are on the field?

  • A . F4
  • B . F1
  • C . F11
  • D . Application help
  • E . System help

Reveal Solution Hide Solution

Correct Answer: B
Question #13

Which feature does SAP S/4HANA include? choose 2 answer

  • A . unchanged data model
  • B . in-memory platform
  • C . support of any database
  • D . SAPUI5-Based UI

Reveal Solution Hide Solution

Correct Answer: B,D
Question #14

The planner add a stock material in the orders .

What does the system create reservation depending on the settings of the order type? choose 2 answers

  • A . after the available check is performed
  • B . when the order is released
  • C . when the order is saved
  • D . when the cost are determined

Reveal Solution Hide Solution

Correct Answer: B,C
Question #15

Which of the following is not a Customizing setting for order types?

  • A . Structure indicator
  • B . Settlement profile
  • C . Planning plant
  • D . Residence time
  • E . Settlement rule

Reveal Solution Hide Solution

Correct Answer: A
Question #16

In which product does SAP deliver embedded analytics? choose 1 answer

  • A . SAP Business warehouse
  • B . SAP S/4HANA
  • C . SAP Business intellignece
  • D . SAP BW/4HANA

Reveal Solution Hide Solution

Correct Answer: B
Question #17

What are the effects when the planner release a maintenance order? choose 3 answers

  • A . the planner can estimate costs
  • B . the planner CANNOT change planned costs
  • C . the planner can print the job papers
  • D . the technician can record confirmations
  • E . the warehouse clerk can post a goods issue

Reveal Solution Hide Solution

Correct Answer: C,D,E
Question #18

What must you maintain before you create the measuring point or counters for technical objects? choose 1 answer

  • A . enter an annual estimate
  • B . create a code group in the necssary catalog
  • C . assign characterisics to classes
  • D . create necssary characterisitics in the calssification system

Reveal Solution Hide Solution

Correct Answer: D
Question #19

Which operations can the responsible person preform after a maintenance order in technically completed? choose 3 answers

  • A . lock or unlock the order
  • B . create invoice receipt for delivered material
  • C . change the planned cost
  • D . change the settelement rule
  • E . update the estimate cost

Reveal Solution Hide Solution

Correct Answer: A,B,D
Question #20

What is the purpose of the SAP GUI Bleize Theme? choose 1 answer

  • A . create a similaire user experience as in SAP fiori launchpad
  • B . make web dynpro app available for SAP GUI
  • C . make SAPUI5 app available for SAP GUI
  • D . create a simplified copy of a transaction

Reveal Solution Hide Solution

Correct Answer: A

Question #21

Why was the application code completely rewritten for SAP S/4HANA?

  • A . To take advantage of the simpler data model
  • B . SAP S/4HANA is now built with Java
  • C . The optimized ABAP code that we developed for Suite on SAP HANA would not work with SAP S/4HANA
  • D . To ensure that the code is optimized for SAP HANA

Reveal Solution Hide Solution

Correct Answer: A,D
Question #22

The maintenance engineer creates a singel cycle plan with the following parameters:

* the call object is maintenance order

* the indicator or seprate completion of maintenance call date is NOT set

* the indicator for completion requirement is NOT activated

* both shift factors are set to 100% .

Which date is relevant for the calculation for further planned dates for all objects? choose 1 answer

  • A . planned date of the next call number
  • B . completion date of maintenance plan
  • C . technical completion date of the maintenance order
  • D . basic finish date of the maintenance order

Reveal Solution Hide Solution

Correct Answer: A
Question #23

In cost control, which of the following represents a closed system for cost accountingpurposes?

  • A . Company code
  • B . Work center
  • C . Controlling area
  • D . Business area

Reveal Solution Hide Solution

Correct Answer: C
Question #24

Why do you create maintenance planner group? choose 1 answer

  • A . to map a group of persons which plan maintenance budgets
  • B . to map a group of persons responsible for maintenance plans
  • C . to map a group of persons responsible for maintenance strategies
  • D . to map a group of persons which plans maintenance activities for technical objects

Reveal Solution Hide Solution

Correct Answer: D
Question #25

What is the purpose of the initial and subsequent buffers in a maintenance strategy? choose 1 answer

  • A . to set the call date
  • B . to set the start date of the maintenance plan
  • C . to set the start/end date of the maintenance order
  • D . to set the planned date

Reveal Solution Hide Solution

Correct Answer: C
Question #26

You create a revision for a maintance event builder (MEB) scenario. which objects can manually assign to a revision? choose 2 answers

  • A . automatically created maintenance order from a maintenance plan
  • B . automatically created notification from a maintenance plan
  • C . manually created notifications
  • D . manually created maintenance orders

Reveal Solution Hide Solution

Correct Answer: B,C
Question #27

Which parameters are calcluated during shceduling of a performance-based maintenance plan? choose 2 answers

  • A . planned date based on sum of counter readings
  • B . monthly performance based on annual estimate
  • C . daily performance based on on annual estimate
  • D . planned date based on cycle and daily performance

Reveal Solution Hide Solution

Correct Answer: C,D
Question #28

You have several defective parts that you need to send to a subcontractor to get them refurbished, what must you do to trigger the external refurbishment order? choose 1 answer

  • A . creat a manual purchase order and add the refuribshment order number
  • B . create an external activity (PM 02) within the refurbishment order
  • C . create a manual purchase requistion and add the refurbishment order number
  • D . create an internal activity (PM 01) and add the defective mateiral as non stock component

Reveal Solution Hide Solution

Correct Answer: B
Question #29

Which valuation category do you use to refurish the material? choose 1 answer

  • A . in-house/ external procurment
  • B . retail
  • C . origin
  • D . condition-based

Reveal Solution Hide Solution

Correct Answer: D
Question #30

In the document management system, you can create new documents that contain information about equipment or repair instructions, and attach these to the maintenance order or operation.

  • A . False
  • B . True

Reveal Solution Hide Solution

Correct Answer: B

Question #31

Which of the following statements about commitments management are correct?

  • A . Commitment values can exceed planned costs.
  • B . Commitments lead to actual costs as a result of various business transactions.
  • C . Commitments are contractual obligations that are entered in accounting.
  • D . Commitments are used to update and monitor resources that are required for external procurement.
  • E . Commitment data is built up when the scheduled order resources are valuated.

Reveal Solution Hide Solution

Correct Answer: A,B,D,E
Question #32

Which of the following areas are available in SAP S/4HANA?

  • A . Concur
  • B . Marketing
  • C . SuccessFactors Employee Central
  • D . Enterprise Management

Reveal Solution Hide Solution

Correct Answer: B,D
Question #33

What is a caracteristics of the SAP Fiori tile group? choose 1 answer

  • A . it is assigned using the set/get parameteres
  • B . it provide an invisible group of SAP Fiori catalogs
  • C . it shows active tiles in SAP fiori launchpad
  • D . it is a building block of the SAP fiori catalog

Reveal Solution Hide Solution

Correct Answer: C
Question #34

With SAP S/4HANA embedded analytics, which tools are aimed at end users?

  • A . Analytical SAP Fiori applications
  • B . SAP Smart Business cockpits
  • C . Design Studio
  • D . Query Designer
  • E . Query Browser

Reveal Solution Hide Solution

Correct Answer: A,B,E
Question #35

Two maintenance package of a maintenance strategy are due at the same time .

Which parameter determine that only one of these maintenance package is executed? choose 1 answer

  • A . hierarchy
  • B . package sequence
  • C . offset
  • D . lead float

Reveal Solution Hide Solution

Correct Answer: A
Question #36

Which of the following pieces of information are available in the production order?

  • A . Order components
  • B . Order costs
  • C . Production dates
  • D . Production instructions
  • E . All of the above
  • F . None of the above

Reveal Solution Hide Solution

Correct Answer: E
Question #37

During the implementation project, you need to define the organizational units .

Which of the following objects can you directly assign a maintenance plant?

  • A . location
  • B . maintenance planner group
  • C . controlling area
  • D . maintenance work center

Reveal Solution Hide Solution

Correct Answer: A
Question #38

Which one of the following relationship types means that the end of one operation is linked to the start of the next operation?

  • A . Start – Start
  • B . Finish – Finish
  • C . Finish – Start
  • D . Start – Finish

Reveal Solution Hide Solution

Correct Answer: C
Question #39

What is a prerequisit to start a performance-based maintenance plan? choose 1 answer

  • A . cycle modification factor
  • B . call horizon
  • C . intial measurement document
  • D . scheduling period

Reveal Solution Hide Solution

Correct Answer: C
Question #40

Which object combination influences the display of the fleet-specific tab strip and fields? choose 1 answer

  • A . equipement category and measuring point category
  • B . fleet object type and vehicle usage indicator
  • C . equipment category and fleet object type
  • D . fleet object type and measuring point category

Reveal Solution Hide Solution

Correct Answer: C

Question #41

Which of the following objects can you directly assign when you define the work center master record? choose 2 answers

  • A . calculation key
  • B . business partner
  • C . capacity category
  • D . orgnaizational unit

Reveal Solution Hide Solution

Correct Answer: C,D
Question #42

Which of the following provides general information on the SAP system and transaction or task on which you are working?

  • A . Menu path
  • B . Role bar
  • C . Application toolbar
  • D . Status bar

Reveal Solution Hide Solution

Correct Answer: D
Question #43

Which of the following are true statements about master data?

  • A . Master data is organized into views that are assigned to organizational elements.
  • B . Master data is created centrally and is available to all applications and allauthorized users.
  • C . Master data decreases data redundancy.

Reveal Solution Hide Solution

Correct Answer: A,B,C
Question #44

Which of the following is true about SAP Asset Intelligence Network cloud application?

  • A . It is the target of the application to maintain a global directory of pieces ofequipment, that uses general definitions.
  • B . A remote service technician is a typical user of this application.
  • C . It is the target of the application, to improve the visibility of machines.
  • D . A constructing engineer is the typical user of this application.

Reveal Solution Hide Solution

Correct Answer: A,D
Question #45

Where can the planner check the material availbility? choose 3 answer

  • A . within the SAP fiori-based background job
  • B . from the list of orders
  • C . within an individual order
  • D . within the SAP fiori-based material document overview
  • E . from the reservation list

Reveal Solution Hide Solution

Correct Answer: B,C,E
Question #46

What does the structure indicator define? choose 2 answers

  • A . the field selection for the functional location list
  • B . the cateogry of the functional Icoation
  • C . the allowed characters for a functional location
  • D . the hierarchy levels of the functional location structure

Reveal Solution Hide Solution

Correct Answer: C,D
Question #47

Which of the following statements about configuring the notification screen are correct?

  • A . You can apply a simple view or an enhanced view to each notification type.
  • B . You can define only one screen area per tab.
  • C . You can assign internal headings and symbols to tabs.
  • D . You can choose from 27 different tab pages for each notification type.

Reveal Solution Hide Solution

Correct Answer: A,C,D
Question #48

In which object can you change the offset of a maintenance plan strategy? choose 1 answer

  • A . maintenance package
  • B . maintenance plan header
  • C . maintenance plan item
  • D . maintenance plan category

Reveal Solution Hide Solution

Correct Answer: A
Question #49

You use SAP Work manager .

Which operation can the maintenance worker execute? choose 2 answer

  • A . change BOM
    create work order on the ESRI map
  • B . create notification
    crearte a measuring reading
  • C . scheduling resources
    change task list
  • D . create equipment
    install equipment

Reveal Solution Hide Solution

Correct Answer: B,D
Question #50

what can planner monitor with the resource scheduling for maintenance planner sap fiori app? choose 2 answers

  • A . workload of wok centers
  • B . maintenance order NOT confirmed
  • C . Notification without maintenance orders
  • D . non-available stock materials

Reveal Solution Hide Solution

Correct Answer: A,B
Exit mobile version