You are using budgeting and active availability control.
How can availability control be activated? Note: There are 2 correct answers to this question
- A . Automatic activation with budget assignment
- B . Automatic activation with assignment to an investment program
- C . Background activation (CJBV – Activate Availability Control) l
- D . Automatic activation with the first actual posting
Your customer’s projects are subject to recurring changes of date. The assembly activity has an earliest start date of February 10 and lasts until February 20. The customer wants to assign a material component so that this will be in stock 5 days in advance. Note: Every day is a working day.
What do you recommend to set up the requirement date for the component?
- A . Set up the requirement date aligned with the activity finish date and an offset of 15 days.
- B . Set up the requirement date manually as February 5.
- C . Set up the requirement date aligned with the activity start date and an offset of 5 days
- D . Set up the requirement date aligned with the activity start date and a negative offset of 5 days
Project Structures
You want to enable user fields for customer project. Therefore you create several field keys.
What is the benefit of assigning a field key to the project profile?
- A . The field key is the default value for the WBS element and the activities too.
- B . The tab user fields is invisible.
- C . The field key is hard coded in the WBS element.
- D . The field key is the default value only for the WBS element.
How can you record external service activities with service master data? Note: There are 2 correct answers to this question
- A . Confirm the network activity for external service
- B . Confirm the activities in the Cross-Application Time Sheet (CATS)
- C . Post a goods receipt in the goods movement application (MIGO)
- D . Create a service entry sheet
The__________________that you specify when you create a project definition is unique for the entire project. Choose the correct answer.
- A . Plant
- B . Controlling area
- C . Company code
- D . Planning department
A service company uses project management and they complain that the system does not prevent their project managers from exceeding their budgets.
What actions do you have to take to solve the problem?
- A . Activate availability control for the WBS elements. Define the tolerance limits on each WBS element
- B . Activate availability control in the assigned budget profile. Define the tolerance limits in customizing
- C . Activate commitment management in the project definition Enter the budget in the master data of the top WBS element
- D . Activate availability control for projects in the controlling area. Enter the plan data for each WBS element
What are valid procurement types for stock items? Note: There are 3 correct answers to this question
- A . Preliminary purchase requisition for WBS element
- B . Planned order
- C . Third-party order
- D . Purchase requisition and Reservation for WBS element
- E . Reservation for WBS element
For which objects can billing plans be created? Note: There are 2 correct answers to this question
- A . WBS elements
- B . Project definition
- C . Sales order items
- D . Milestones
Which sets of dates can be used to schedule networks? Note: There are 2 correct answers to this question
- A . Basic dates
- B . Forecast dates
- C . Baseline dates
- D . Planned dates
Where can you assign the use status profile for WBS elements? Note: There are 3correct answers to this question
- A . In the project profile
- B . In the project version
- C . In the project type
- D . In the project definition of a standard WBS
- E . In the operative WBS element