You have created an internally-processed network activity, and assigned a work center and the work. After saving, you discover that no planned costs are displayed in the cost element report for the activity.
What could be the reason? Note: There are 3 correct answers to this question
- A . The formula for costing in the work center is incorrect
- B . The activity output price for the activity type and cost center assigned to the work center is not maintained.
- C . The duration is missing in the activity
- D . The Determine Costs indicator in the network header rules out planned cost calculation
- E . Integrated planning for the network is active
You used reductions to reduce the scheduled duration of all internally-processed activities in your project. However, the duration did not changed after overall network scheduling.
What do you check? Note: There are 2 correct answers to this question
- A . If the maximum reduction level is less than 100
- B . If the reduction strategy is set in the network header
- C . If the reduction strategy is set in each activity
- D . If the appropriate reduction type is set in the parameters for network scheduling
Project Structures
You are using assembly processing. You need to determine the delivery date of a sales order item with an account assignment to the
project.
What are the prerequisites? Note: There are 3 correct answers to this question
- A . A bill of material with sales views
- B . A material master with sales views
- C . Assignment between material and standard network
- D . Standard network with activities
- E . A production order
You use networks and internal activities in your project. You have activated capacity requirements and notice that one work center is overloaded. You have no authorization to change the work center.
How can you reduce the overload of the work center? Note: There are 2 correct answers to this question
- A . Maintain subordinate internal activity elements assigned to other work centres
- B . Increase the capacities of the work center in the project planning board.
- C . Trigger automatic capacity leveling inside the project planning board
- D . Shift activities backward or forward on the time axis where more capacities are available
Materials
Your customer use a tight (estrecha) integration between sales order and WBS with network to deliver finished and semi-finish product.
What benefit do they have when using delivery from project (CNSO)?
- A . With delivery from projects You can generate goods issues for project without creating delivery documents.
- B . With delivery from projects good receipt are automatically posted while saving.
- C . With delivery from projects you can generate purchase requisitions for sub-contractors.
- D . With the delivery from project you can deliver material component assigned to your network.
You want to use subnetworks during the project.
Which of the following statements describes subnetworks?
- A . Maintenance orders can be defined as sub-network
- B . The scheduling type of a subnetwork is always copied from the superior network
- C . A subnetwork cannot be defined for a superior subnetwork.
- D . Subnetworks must be scheduled separately from the superior network
Which object is used to allocate the costs from a claim to the project structure?
- A . Network activity
- B . Internal order
- C . Claim
- D . WBS element
Which of the following data can be maintained in a standard network? Note: There are 3 correct answers to this question
- A . Document information records
- B . Internally processed activities
- C . Basic dates for activities
- D . Material components
- E . Relationships
Project Structures
Which the following statement regarding networks are correct? Note: there are 3 correct answers for this question.
- A . If a network activity requires more capacity than available in a work center, the system automatically proposes an alternative work center.
- B . You can assign more than one activity element to a network activity.
- C . Capacity requirements of a network activity are reduced when the activity is confirmed.
- D . During scheduling, the system plans the network activities in such a way that the assigned work center are not overloaded in terms of capacity.
- E . You can assign the same work center to more than one activity on the same network.
How are earliest dates and latest dates of activities scheduled?
- A . Earliest dates are scheduled by backward scheduling, and latest dates by copying the earliest dates
- B . Earliest dates are scheduled by forward scheduling, and latest dates by backward scheduling
- C . Earliest dates and latest dates are scheduled by forward scheduling
- D . Earliest dates are scheduled by backward scheduling, and latest dates by forward scheduling