You plan an activity that starts on February 1 and finishes on February 28. For this activity, you want to define a milestone for February 10 which should NOT be changed through scheduling.
What do you recommend for milestone definition?
- A . Enter an offset of -18 days to the finish date of the activity
- B . Enter February 10 as fixed date
- C . Enter 10 days as duration
- D . Enter an offset of 10 days to the start date of the activity
What are the prerequisites for delivering materials from the project? Note: There are 2 correct answers to this question
- A . A delivery document type must be configured
- B . A sold to party is necessary
- C . A shipping point is necessary
- D . A sales order must be created in advance
Material
Your customer uses Progress Tracking for network components and mantains dates of events manually. They need to implement scheduling of events.
What is the requisites for implement scheduling of events?
- A . Priority of events must be set.
- B . Scheduling parameters for material scheduling must be set.
- C . Events must be released manually.
- D . Event scenarios must be defined.
You are using WBS elements and activities are NOT assigned.
Which statements apply to the maintenance of the actual start and finish? Note: There are 2 correct answers to this question
- A . You can only maintain the actual finish if all lower-level WBS elements have an actual finish date and the status of the WBS element is "Released"
- B . You can always maintain the actual start if the WBS element has the status "Released" or "Partially released"
- C . You can always maintain the actual start and finish date of a WBS element
- D . You can only maintain the actual start of a WBS element if the finish date is not maintained
Dates
You have a project with a network, material and milestone. You want to plan an activity to start two days after its predecessor.
How can you do that? Note: there are 2 correct answers for this question.
- A . Use an offset of two days for the relationship of both activities.
- B . Use an offset of two days for milestone date.
- C . Use an offset of two days for the requirement date of the material component
- D . Calculate the start date of the activity and set the constraint "Must start on" accordingly.
You have saved a network and activates with assigned material components. As soon as you release the network, you receive the error message "Business transaction cannot be carried out" What could be the reason for this error message?
- A . Missing budget for material components
- B . Missing reservations for material components
- C . Missing material availability
- D . Missing authorizations to release material components
How can you grant individual authorization for WBS elements and networks?
- A . Define a user status to lock the business transaction Update Project.
- B . Set the system status to "Lock Master Data".
- C . Activate access control lists (ACL) for the user master record.
- D . Activate access control lists (ACL) for the project profile and the network profile
You want to determine the planned costs for an internally processed activity.
Which data do you need Note: There are 2 correct answers to this question
- A . Duration
- B . Activity type
- C . Work
- D . Profit center
An external component is assigned to a network activity. The delivery date for the purchase requisition depends on the dates of the network activity.
What controls whether the delivery date is defined by the earliest or latest scheduled dates?
- A . The network profile
- B . The control key
- C . The table of MRP controllers
- D . The scheduling parameters for the network
Revenues & Payment
Your customer wants to plans and post revenues for WBS elements.
What is crucial for the implementation of revenues planning and posting for WBS elements?
- A . At least one WBS element must be a billing element.
- B . The indicator "Project type" must be set to "Customer project".
- C . Revenue planning and billing must be activated in the corresponding network type.
- D . A sales order item has to be assigned to each WBS element used for revenue planning.