You are using WBS elements and activities are NOT assigned.
Which statements apply to the maintenance of the actual start and finish? Note: There are 2 correct answers to this question
- A . You can only maintain the actual finish if all lower-level WBS elements have an actual finish date and the status of the WBS element is "Released"
- B . You can always maintain the actual start if the WBS element has the status "Released"
or "Partially released" - C . You can always maintain the actual start and finish date of a WBS element
- D . You can only maintain the actual start of a WBS element if the finish date is not maintained
What are some of the possible functions in user status profiles? Note: There are 2 correct answers to this question.
- A . Ensure user status must always be set manually
- B . Allow business processes forbidden by SAP system status
- C . Restrict setting user status for individual users
- D . Utilize priorities for setting the user status
Resources
Which of the following transactions can you use to post actual cost for external processing? Note: there are 2 correct answer for this question.
- A . Approval of a service entry sheet
- B . Posting a goods receipt
- C . Creating a service entry sheet
- D . Approval of a good receipt.
- E . Creating a purchase order.
What are the prerequisites for delivering materials from the project? Note: There are 2 correct answers to this question
- A . A delivery document type must be configured
- B . A sold to party is necessary
- C . A shipping point is necessary
- D . A sales order must be created in advance
You are working with networks and WBS elements.
Which of the following statements applies?
- A . You can reassign an activity from one network to another
- B . You can assign the network header to multiple WBS elements
- C . You have to maintain a network profile in the project profile
- D . You have to activate the operative indicator Account Assignment Element for WBS element with activities.
For which objects can billing plans be created? Note: There are 2 correct answers to this question
- A . WBS elements
- B . Project definition
- C . Sales order items
- D . Milestones
Project structure.
You intent to work with predefined project coding mask to create project definitions.
What do you have to consider?
- A . You can create project coding mask X… event if there are project numbers beginning with X.
- B . The standard project definition must differ from the definition of the operative project.
- C . You can use only numbers for a project coding mask definition.
- D . You can use an indicator to determine that only coded project numbers may be used within the project system.
A component is assigned to a network activity.
What are the prerequisites to generate project stock reservations? Note: There are 3 correct answers to this question
- A . The network activity is assigned to a WBS element
- B . The network is assigned to a sales order item
- C . The material master of the component must permit project stock management
- D . The Project Stock indicator is set in the project definition (non-valuated or valuated)
- E . A procurement indicator must be assigned to the activity
The basic dates of subordinate WBS elements should be extrapolated without taking into account the basic dates of higher-level WBS elements.
What planning method for basic dates do you use?
- A . Free planning
- B . Top-down
- C . Strict bottom-up
- D . Bottom-up
When you create a service activity in your network, what data can be entered? Note: There are 3 correct answers to this question.
- A . Service specification
- B . Overall limit (maximum value of all unplanned services)
- C . Service purchase order number
- D . Material master within service specification