A customer use cross- company – code project with a top billing element and additional billing element underneath (por debajo) for each company code. Although the internal .. correctly the result analysis summarizes all values to the highest billing element.
How can they split the results to the different company codes?
- A . Settle the WBS element to the highest billing element before you do the result analysis.
- B . Split the project intdifferent project according to each company code.
- C . Change the project structure so that it correspond better to the company’s organization structure.
- D . Adjust the customizing of the valuation method in the expert mode of the periodic results analysis accordingly.
Material
You want to create purchase requisition for the material used in your project. However after releasing the project, no purchase requisition has been created.
What could be the reason? Note: there are 2 correct answers for this question.
- A . The procurement type in the material master is set to in-house Production.
- B . The item category of the materials is set tstock item.
- C . The material have no material number.
- D . The item category of the materials is set tnon-stock item.
Cost & Budget
You are using network and internal activities in your project. You have already create a purchase requisition and the bid invitation., and have entered the quotation …
What is the typical sequence for the following business transactions and document.
- A . Benefic check – Acceptance of performed service- vendor selection – purchase order handing- purchase order monitoring-Good receipt – invoce ..
- B . Vendor selection – purchase order handing- purchase order monitoring- Benefic Check-Acceptance of performed services.
- C . Vendor selection – purchase order handing – invoice receipt – purchase order monitoring -Good receipt.
- D . Vendor selection- Purchase order handing-purchase order monitoring-Good receipt-Invoice receipt.
Project Structures
Which the following statement regarding networks are correct? Note: there are 3 correct answers for this question.
- A . If a network activity requires more capacity than available in a work center, the system automatically proposes an alternative work center.
- B . You can assign more than one activity element to a network activity.
- C . Capacity requirements of a network activity are reduced when the activity is confirmed.
- D . During scheduling, the system plans the network activities in such a way that the assigned work center are not overloaded in terms of capacity.
- E . You can assign the same work center to more than one activity on the same network.
Which report can use user-specific layouts?
- A . Line item report
- B . Enhanced individual overview
- C . Cost element report
- D . Hierarchical report
Which objects do you have to maintain to enable automatic assignment of material components to the project? Note: There are 2 correct answers to this question
- A . Material master
- B . Network activity
- C . WBS element
- D . BOM item
Resources
You Want assign milestone to WBS element? For what can you use these milestone.
- A . To create standard network
- B . To start workflow task.
- C . For trend analysis.
- D . To set an actual finish date for WBS element-
Resources
How can you define external task in your project. Note: there are 2 correct answers for this question.
- A . Assign a purchase order for external processing to the project definition.
- B . Create an external activity in a network.
- C . Create a service milestone.
- D . Create a service activity in a network.
Dates
You have a project with a network, material and milestone. You want to plan an activity to start two days after its predecessor.
How can you do that? Note: there are 2 correct answers for this question.
- A . Use an offset of two days for the relationship of both activities.
- B . Use an offset of two days for milestone date.
- C . Use an offset of two days for the requirement date of the material component
- D . Calculate the start date of the activity and set the constraint "Must start on" accordingly.
Which of the following statements are true? Choose the correct answers. There are 2 correct answers to this question.
- A . You can map a project using only one WBS or one network.
- B . You can also represent a project using a WBS and one or more networks.
- C . You can create a project based on a Activity.
- D . You cannot use the characteristics of both the structures (WBS and Networks) together to represent a project.