In SAP Enterprise Portfolio and Project Management, which objects can be used to exchange data back and forth to other application objects? Note: There are 2 correct answers to this question
- A . Project task and network activity
- B . Project phase and WBS element
- C . Portfolio item and Project System project definition
- D . Milestone task and WBS element
Which of the following multi-currency scenario are supported? NOTE: There are 2 correct answers to this question
- A . Multiple planning currencies can be used in one bucket
- B . Item currency can be inherited from the assigned bucket
- C . Bucket in a portfolio can use different currencies
- D . Items In a bucket an only use bucket currencies
What innovation management object is linked to SAP portfolio and project management (PPM) out of the box?
- A . Opportunity
- B . Idea
- C . Campaign
- D . Request
You want to split the financial planning values of portfolio item into two different buckets.
How do you do this?
- A . Enable financial planning for multiple buckets
* Assign additional buckets in financial planning
* Maintain factors to split financial planning of the item. - B . Enable the split of financial values for the item type.
* Assign the item to two bucket of the classification hierarchy
* Maintain factors to split financial planning of the item - C . Enable the split of financial values for the item type
* Assign the item to two bucket of the portfolio
* Maintain factors to split financial planning of the item - D . Enable process change for multiple buckets.
* Start process change to reassign the item two buckets
* Maintain factors to split financial planning of the item
You want to distribute capacity requirements in a project management project?
How can you distribute the values? NOTE: There are 3 correct answers to this question
- A . Use a distribution function
- B . Copy values from resource assignments
- C . Apply a distribution rule
- D . Update the capacity requirements from the roll-up of task requirements
- E . Enter the vales manually
Which customizing activity do you use to integrate capacity planning of an item with financial planning?
- A . Define financial integration scenarios
- B . Define portfolio type
- C . Define financial and capacity views
- D . Define financial planning settings
Which information can be assigned to a business partner in project management? NOTE: There are 3 correct answers to this question
- A . Work centers
- B . Areas and locations
- C . Personal numbers
- D . Production resources or tools (PRT)
- E . SAP users
You have created a custom field and want to add this field to the item dashboard.
Where do you have to select the field to achieve this? NOTE: There are correct answers to this question.
- A . In the BCV settings for the item dashboard
- B . In the item dashboard settings
- C . In customizing for item dashboard fields
- D . In the Launchpad settings for the item dashboard
You customer wants to involve the project manager, the staffing manager, and the candidate manager in the staffing of a project management project.
Which process requires a status change for each process step?
- A . Role assignment and staffing
- B . Staffing by authorization
- C . Extended staffing
- D . Qualification determination
You are planning resources.
Which period types are available? NOTE: There are 3 correct answers to this question.
- A . Weekly
- B . Hourly
- C . Monthly
- D . Daily