You are in portfolio management and create a project system (PS) project from an item.
Which parts you add afterwards directly in PS? NOTE: There are 3 correct answers to this question
- A . Network activities
- B . PS texts
- C . Documents
- D . Network components
- E . WBS elements
No upcoming milestone are shown in the my projects SAP Fiori app.
What are the reasons for this? NOTE: There are 2 correct answers to this question
- A . You are not defined as the project Responsible
- B . Milestone is not identified as mandatory
- C . Project is not released
- D . Milestone is not identified ascritical
Which system behavior are enabled when a create a project with multiple phase? NOTE: There are 2 correct answers to this question.
- A . Determination of the start-dates of subsequent phases
- B . Rollup of activity cost allocations to phases
- C . Rollup of resource requirements of tasks to phases
- D . Determination of the start- and end-dates of tasks
In project management, a WBS element for accounting integration was created automatically.
What is used to calculate the planned costs of this WBS element? NOTE: There are 3 correct answers to this question
- A . Staffing of work in the role
- B . Duration planned on project tasks
- C . Demand planned on project roles
- D . Work planned on project task
What is a prerequisite for using role charts in project management?
- A . The demand of a role must have been updated according to tasks
- B . A graphic profile is assigned to the role type
- C . A graphic profile is assigned to the project type
- D . The demand of a role must be distributed over a number of periods
How are capacity planning values rolled up along the bucket hierarchy?
- A . Item values are rolled up to buckets via the collection
- B . Item values are rolled up to buckets via the review
- C . Item values are rolled up directly to buckets
- D . Project values are rolled up directly to buckets
How can an existing project management project be integrated with SAP controlling? NOTE: There are 2 correct answers to this question.
- A . Assign the project definition to an existing PS project definition manually
- B . Transfer the project structure element to project system (PS)
- C . Transfer the project structure element internal orders
- D . Assign the project roles to an existing internal order manually
Where can you create a status for a what-if scenario in portfolio management/
- A . In the what-if scenario classification
- B . In the review
- C . In the what-if scenario type
- D . In customizing for the portfolio type
What must you do before you can use multiple currencies in financial planning in portfolio management?
- A . Select multiple currencies in the portfolio definition
- B . Define a subnet of currencies in portfolio and project management
- C . Select multiple currencies in the portfolio item
- D . Define a subnet of currencies in project system
Which of the project definition in project management must be filled before you can release a project?
- A . End date
- B . Responsible
- C . Project type
- D . Controlling area