You have created a portfolio with the bucket levels and wants to create a portfolio item.
When can you create the portfolio item?
- A . At any bucket level
- B . At the highest bucket level
- C . At multiple bucket levels
- D . At the lowest bucket level
What can you define in the item template?
- A . Category
- B . Link to a project management project
- C . Sequence of decision points
- D . Financial planning
What are dashboard alerts calculations based on?
- A . Percentage values
- B . Numeric values (Specified range)
- C . Business Add-in (BAdi) implementation
- D . The status fields
Which cost planning process can you use at item level? NOTE: There are 2 correct answers to this question.
- A . Integrated cost planning
- B . Hierarchical cost planning
- C . Manual cost planning
- D . Rollup of cost planning
Which of the following are search criteria In Resource Search in Project Management? NOTE: There are 2 correct answers to this question.
- A . Work centers
- B . Organizational units
- C . Qualifications
- D . plants
Which of the following are consequence of releasing a phase? NOTE: There are 2 correct answers to this question
- A . Predecessor phases are assigned the status locked
- B . Lower-level tasks and checklist are release
- C . Additional tasks cannot be added to the phase
- D . The phase type is set to read-only
You have created a role in project management but the role is not displayed on the fast entry screen.
What could be the reason for this?
- A . The flexible Assignment indicator is active in role type customizing
- B . The role has the staffing in preparation status
- C . The role has the staffing in process status
- D . The Distribution indicator is active role type customizing
Which data is transferred when you import a Microsoft project management?
- A . Task
- B . Authorizations
- C . Status reports
- D . Cost
When are decision points for portfolio items created?
- A . After approval of an item
- B . During master date maintenance of an item
- C . During creation of an item
- D . After planning of financial values of an item
You want to add a report to the side panel of the item detail screen. The new report should display the upto-date financial planning values for the item.
Which reporting tool do you use?
- A . Portfolio dashboard
- B . Evaluation
- C . BI report
- D . Business Context Viewer (BCV)