SAP C_S4CPS_2208 SAP Certified Application Associate – SAP S/4HANA Cloud (public) – Professional Services Implementation Online Training
SAP C_S4CPS_2208 Online Training
The questions for C_S4CPS_2208 were last updated at Nov 15,2024.
- Exam Code: C_S4CPS_2208
- Exam Name: SAP Certified Application Associate - SAP S/4HANA Cloud (public) - Professional Services Implementation
- Certification Provider: SAP
- Latest update: Nov 15,2024
How is the actual availability of a resource for project assignments calculated?
- A . Available hours = Staffed hours – Free hours
- B . Free hours = Available hours – Staffed hours
- C . Free hours = Staffed hours – Available hours
- D . Available hours = Free hours – Staffed hours
What tasks can the Resource Manager perform through the Fiori apps that are available in the advanced version of Resource Management? Note: There are 2 correct answers to this question.
- A . Staff resource requests for project roles
- B . Transfer actual working times
- C . Maintain skills for work items
- D . Monitor and analyze resource utilization
You are reviewing the Open Resource Requests KPI card in the Fiori app Resource Management for Projects.
What are the possible urgency groupings? Note: There are 2 correct answers to this question.
- A . VeryHigh
- B . Overdue
- C . Upcoming
- D . Critical
Which replication scenarios are supported through the integration between SAP S/4HANA Cloud and SAP SuccessFactors Employee Central? Note: There are 3 correct answers to this question.
- A . Bank data
- B . Employee data
- C . WBS element data
- D . Cost center data
- E . Timesheet data
What are the prerequisites for using the SAP Fiori Test Your Processes app? Note: There are 2 correct answers to this question.
- A . The productive system is connected to the implementation landscape
- B . The test scripts are uploaded in the productive system
- C . SAP Best Practices are activated in the quality system
- D . The quality system is connected to the Test Execution Service on SAP Cloud Platform
Which processes are covered in the SAP Best Practices Internal Project Management – Project- Based Services (1A8) scenario? Note: There are 2 correct answers to this question.
- A . Perform margin analysis
- B . Maintain work package staffing
- C . Capture service units
- D . Perform period-end closing activities
What are key activitiesof the Prepare phase of the SAP Activate methodology? Note: There are 3 correct answers to this question.
- A . Project setup
- B . Customer self-enablement
- C . Data migration
- D . Starter system provisioning
- E . User training
How does the system determine the default currency for an internal project?
- A . From the user default settings
- B . From the controlling area of the profit center
- C . From the settings of the Create Internal Project app
- D . From the company code of the service organization
Which of the following aremandatory fields when running a settlement for an internal project? Note: There are 3 correct answers to this question.
- A . Test Run
- B . Posting period
- C . Processing type
- D . Fiscal Year
- E . Settlement period
Which organizational unitsare directly linked to a plant? Note: There are 2 correct answers to this question.
- A . Company code
- B . Credit control area
- C . Storage location
- D . Sales office