Question #1

Which of the following transaction rules can the buyer enable during scheduling agreement configuration? Note: There are 3 correct answers to this question.

  • A . Allow suppliers to use only JIT for shipping
  • B . Allow suppliers to send order confirmations for scheduling agreements and scheduling agreement releases.
  • C . Allow suppliers to use only Forecast for shipping
  • D . Allow suppliers to use both JIT type and Forecast type releases for shipping
  • E . Allow suppliers to update scheduling agreements

Reveal Solution Hide Solution

Correct Answer: A,B,C
Question #2

Which SAP modules have the ability to integrate with Ariba Forecast Collaboration? Note:

There are 2 correct answers to this question.

  • A . SAP Integrated Business Planning (IBP)
  • B . SAP Intelligent Product Planning (IPP)
  • C . SAP Enterprise Resource Planning (ERP)
  • D . SAP Advanced Planner and Optimizer (APO)

Reveal Solution Hide Solution

Correct Answer: A,C
Question #3

Where would a user maintain cross-reference configuration parameters during purchase order collaboration setup?

  • A . SAP Project Reference Object (SPRO)
  • B . Default Transaction Rules on Ariba Network (AN)
  • C . Integrated Business Planning (IBP)
  • D . Cloud Integration Gateway (CIG)

Reveal Solution Hide Solution

Correct Answer: D
Question #4

Which of the following are sources of forecast data from the ERP? Note: There are 2 correct answers to this question.

  • A . Planned order
  • B . Purchase requisition
  • C . Planned independent requirement
  • D . Production Order

Reveal Solution Hide Solution

Correct Answer: A,B
Question #5

Which of the following processes are included in Quality Collaboration? Note: There are 2 correct answers to this question.

  • A . Quality notification
  • B . Cost of quality
  • C . Quality review
  • D . Quality of invoice

Reveal Solution Hide Solution

Correct Answer: A,C
Question #6

Which cXML message is used to send Planned Shipment data?

  • A . Order Request Message
  • B . Product Activity Message
  • C . Product Replenishment Message
  • D . Receipt Request Message

Reveal Solution Hide Solution

Correct Answer: B
Question #7

At which levels can Ariba Network Business Transaction Rules be maintained? Note: There are 3 correct answers to this question

  • A . Supplier level
  • B . Default level
  • C . Supplier group level
  • D . Buyer group level
  • E . Country based invoicing level

Reveal Solution Hide Solution

Correct Answer: A,B,C
Question #8

Which message types are specific to the subcontracting process only? Note: There are 2 correct answers to this question.

  • A . Goods receipt
  • B . ERS Invoice
  • C . Subcontracting purchase order
  • D . Component receipt

Reveal Solution Hide Solution

Correct Answer: C,D
Question #9

Which SAP ERP movement type is used for Returns Collaboration

  • A . 561
  • B . 101
  • C . 161
  • D . 105

Reveal Solution Hide Solution

Correct Answer: C
Question #10

Which of the following are types of inspection characteristics? Note: There are 2 correct answers to this question.

  • A . Physical
  • B . Quantitative
  • C . Engineering
  • D . Qualitative

Reveal Solution Hide Solution

Correct Answer: B,D

Question #11

When does the buyer update the status of the Quality Notification to "Complete?

  • A . When the Quality Notificationis updated with a root cause
  • B . When the Inspection Lot is accepted
  • C . When the Quality Notification is closed
  • D . When the Advance Ship Notice is delivered

Reveal Solution Hide Solution

Correct Answer: A
Question #12

When will an invoice be generated in the Evaluated Receipt Settlement (ERS) process?

  • A . After purchase order confirmation
  • B . After purchase order
  • C . After goods receipt
  • D . After inbound delivery

Reveal Solution Hide Solution

Correct Answer: C
Question #13

When does the Quality Inspection occur for Quality Collaboration in Ariba Network

  • A . Before ASN
  • B . After invoice
  • C . Before order confirmation
  • D . Before invoice

Reveal Solution Hide Solution

Correct Answer: A
Question #14

The detail screen of Individual Data Planning in Supplier Managed Inventory gives sellers the ability to enter which of the following quantities?

  • A . Stock level quantity
  • B . Planned shipmentquantity
  • C . Net requirements quantity
  • D . In transit quantity

Reveal Solution Hide Solution

Correct Answer: B
Question #15

How is a replenishment order displayed on the supplier side in Ariba Network?

  • A . Production Order
  • B . Firmed Order
  • C . Purchase Order
  • D . Sales Order

Reveal Solution Hide Solution

Correct Answer: B
Question #16

Which supplier document informs the buyer that finished goods production is complete?

  • A . Component Consumption
  • B . Order Confirmation
  • C . Inventory Status
  • D . Advance Ship Notice

Reveal Solution Hide Solution

Correct Answer: D
Question #17

Which documents are part of SAP Ariba Purchase Order Collaboration? Note: There are 3 correct answers to this question.

  • A . Advance Ship Notice
  • B . Order Confirmation
  • C . Goods Receipt
  • D . Forecast Commit
  • E . Quality Inspection

Reveal Solution Hide Solution

Correct Answer: A,B,C
Question #18

Which of the following items are recorded on an Inspection Lot? Note: There are 2 correct answers to this question.

  • A . Customer Complaint
  • B . Inspection Results
  • C . Quality Task
  • D . Usage Decision

Reveal Solution Hide Solution

Correct Answer: B,D
Question #19

What are the integration options for B2B suppliers? Note: There are 2 correct answers to this question.

  • A . Notepad Upload/Download
  • B . cXML
  • C . POS (Point of Sale)
  • D . Dedi

Reveal Solution Hide Solution

Correct Answer: B,D
Question #20

Which of the following documents are sent to the subcontractor as a copy document? Note:

There are 2correct answers to this question.

  • A . Component Supplier Create Invoice
  • B . Buyer Create PO Sent to Component Supplier
  • C . Component Supplier Create Ship Notice
  • D . Buyer Create Component Consumption

Reveal Solution Hide Solution

Correct Answer: B,C

Question #21

In which planning horizon zone are suppliers allowed to create a ship notice?

  • A . Trade-off Zone
  • B . Planning Zone
  • C . Firm Zone
  • D . Committed Zone

Reveal Solution Hide Solution

Correct Answer: C
Question #22

Which of the following are benefits of Forecast Collaboration? Note: There are 2 correct answers to this question

  • A . Defers transfer and payment of goods until they are consumed
  • B . Reduces uncertainty between trading partners and leads to consolidated supply chain inventories
  • C . Allows suppliers to allocate production capacity and inventory against buyer’s projected demand
  • D . Increases inventory levels

Reveal Solution Hide Solution

Correct Answer: B,C
Question #23

Which alerts are provided within the Supply Chain Monitor? Note: There are 3 correct answers to this question.

  • A . Forecast alerts
  • B . Inventory alerts
  • C . Advance ship notice alerts
  • D . Order confirmation alerts
  • E . Planned shipment alerts

Reveal Solution Hide Solution

Correct Answer: A,B,D
Question #24

Which of the following data are displayed on the Quality Inspection header? Note: There are 3 correct answers to this question.

  • A . Batch
  • B . Invoice
  • C . Quantity
  • D . Sales order number
  • E . Purchase order number

Reveal Solution Hide Solution

Correct Answer: B,D,E
Question #25

What are the options available when suppliers create an order confirmation in Ariba Network? Note: There are 3 correct answers to this question

  • A . Deliver Line Item
  • B . Update Line Items
  • C . Approve Entire Order
  • D . Confirm Entire Order
  • E . Reject Entire Order

Reveal Solution Hide Solution

Correct Answer: B,D,E
Question #26

What is the cXML message type for consignment movement?

  • A . Receipt Request
  • B . Ship Notice Request
  • C . Consign Move Request
  • D . Product Activity Message

Reveal Solution Hide Solution

Correct Answer: A
Question #27

What is available in Quality Notification items?

  • A . Defects, tasks, activities, causes
  • B . Priority and defect type
  • C . Qualitative and quantitative characteristics
  • D . Notification details

Reveal Solution Hide Solution

Correct Answer: A
Question #28

Which of the following are possible time bucket views in Ariba Network? Note: There are 2 correct answers to this question.

  • A . Daily
  • B . Hourly
  • C . Biweekly
  • D . Weekly

Reveal Solution Hide Solution

Correct Answer: A,B
Question #29

Which processes apply to component consumption in the subcontracting process? Note: There are 2correct answers to this question.

  • A . In backflush, the contract manufacturer does NOT need to report on the consumption of the components.
  • B . In backflush, the supplier needs to send a consumption report after the components have been used
  • C . In real-time, the supplier needs to send a consumption report after the components have been used.
  • D . In real-time, the contract manufacturer does NOT need to report on the consumption of the component

Reveal Solution Hide Solution

Correct Answer: A,C
Question #30

Which documents can a supplier create from a scheduling agreement release on Ariba Network? Note: There are 2 correct answers to this question.

  • A . Contract request
  • B . Invoice
  • C . Ship notice
  • D . Goods receipt

Reveal Solution Hide Solution

Correct Answer: B,C