In which planning horizon zone are suppliers allowed to create a ship notice?
- A . Trade-off Zone
- B . Planning Zone
- C . Firm Zone
- D . Committed Zone
Which of the following are benefits of Forecast Collaboration? Note: There are 2 correct answers to this question
- A . Defers transfer and payment of goods until they are consumed
- B . Reduces uncertainty between trading partners and leads to consolidated supply chain inventories
- C . Allows suppliers to allocate production capacity and inventory against buyer’s projected demand
- D . Increases inventory levels
Which alerts are provided within the Supply Chain Monitor? Note: There are 3 correct answers to this question.
- A . Forecast alerts
- B . Inventory alerts
- C . Advance ship notice alerts
- D . Order confirmation alerts
- E . Planned shipment alerts
Which of the following data are displayed on the Quality Inspection header? Note: There are 3 correct answers to this question.
- A . Batch
- B . Invoice
- C . Quantity
- D . Sales order number
- E . Purchase order number
What are the options available when suppliers create an order confirmation in Ariba Network? Note: There are 3 correct answers to this question
- A . Deliver Line Item
- B . Update Line Items
- C . Approve Entire Order
- D . Confirm Entire Order
- E . Reject Entire Order
What is the cXML message type for consignment movement?
- A . Receipt Request
- B . Ship Notice Request
- C . Consign Move Request
- D . Product Activity Message
What is available in Quality Notification items?
- A . Defects, tasks, activities, causes
- B . Priority and defect type
- C . Qualitative and quantitative characteristics
- D . Notification details
Which of the following are possible time bucket views in Ariba Network? Note: There are 2 correct answers to this question.
- A . Daily
- B . Hourly
- C . Biweekly
- D . Weekly
Which processes apply to component consumption in the subcontracting process? Note: There are 2correct answers to this question.
- A . In backflush, the contract manufacturer does NOT need to report on the consumption of the components.
- B . In backflush, the supplier needs to send a consumption report after the components have been used
- C . In real-time, the supplier needs to send a consumption report after the components have been used.
- D . In real-time, the contract manufacturer does NOT need to report on the consumption of the component
Which documents can a supplier create from a scheduling agreement release on Ariba Network? Note: There are 2 correct answers to this question.
- A . Contract request
- B . Invoice
- C . Ship notice
- D . Goods receipt